Pavement Design and Construction Game 1

Pavement Design and Construction Game 1

University

6 Qs

quiz-placeholder

Similar activities

webpage creation

webpage creation

11th Grade - University

10 Qs

ADDIE Model dan ASSURE Model

ADDIE Model dan ASSURE Model

University

10 Qs

MODULE 4- INSTRUCTIONAL MODEL QUIZ 1

MODULE 4- INSTRUCTIONAL MODEL QUIZ 1

University

10 Qs

The Automobile

The Automobile

8th Grade - Professional Development

10 Qs

Designing

Designing

7th Grade - University

10 Qs

computers and such

computers and such

University

10 Qs

Checkpoint 2 Review - 12 A

Checkpoint 2 Review - 12 A

12th Grade - University

10 Qs

TECHNOLOGY INTEGRATION

TECHNOLOGY INTEGRATION

University

10 Qs

Pavement Design and Construction Game 1

Pavement Design and Construction Game 1

Assessment

Quiz

Instructional Technology

University

Hard

Created by

HARYATI FKA

Used 7+ times

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Based on AASHTO 1993, what is the performance period in flexible pavement design.

The period of years that an initial pavement life will last before it need reconstruction.

The period of time that an initial pavement structure will last before it need rehabilitation.

The design of pavement that an initial pavement layers before reconstruction.

The design of pavement performance that to sustain the traffic loading .

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Concrete pavement distribute load over wide , therefore , the pressure given on the subgrade is high.

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

AASHTO 1993 Pavement Design Guideline was developed using _____________________ method.

mechanistic empirical

empirical

precedent

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Standard axle load used in ESAL calculation is:

8160 kg

816 kg

80 kg

5.

FILL IN THE BLANK QUESTION

30 sec • 1 pt

What is ESAL

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Assumed that there will be 500 000 ESAL for both directions ( 2 lanes per direction). Estimate the design ESAL with 80% lane distribution.

250 000

300 000

200 000

400 000