BTEC DIT C1 LAB - Project Planning Basics
Authored by Sarah Rodgers
Computers
10th Grade
Used 101+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project life cycle, which stage comes after the design stage?
Testing
Implementation
Specification requirements
Evaluation
2.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Name Two Project Planning Methodologies
Mindmaps
Waterfall
Flowcharts
Agile
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Which of the following do you have to consider when identifying the audience of a user interface. (Choose all that apply)
IT skills
Hair colour
Accessibility needs
Age range
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
"The user interface will have different screens" Is this a SMART objective?
Yes
No
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
"I will spend two hours creating each screen within the user interface" Is this a SMART objective?
Yes
No
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the "T" stand for in SMART when referring to objectives.
Text
Task
Timely
Trend
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which level of It skills does the following statement apply to? "The user will be able to know instinctively what to do without thinking about it"
Expert User
Regular User
Occasional User
Novice User
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?