1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Identify the longest task?

Fill Kettle

Boil Kettle

Put tea in cup

Put sugar in cup

Get milk out of fridge

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

How many tasks are dependent on pouring water into a cup?

1

2

4

5

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

How many seconds form the critical path?

100 seconds

220 seconds

205 seconds

120 seconds

200 seconds

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Critical Path Analysis

A project management technique for process planning that defines critical (milestones) and non-critical tasks

A graphical display of project activities represented by an area of land showing physical features

A set of drawings which consists of floor plan, site plan, and landscape drawings for the ease of construction at site

A colourful diagram, displaying a visual representation of total spending against the time taken to complete a project

5.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Media Image

Which are the activities that immediately preceded activity I?

E

K

F

H

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What is the earliest event time for event 4?

4 days

4 hours

4 minutes

4 weeks

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

What is the latest event time for event 2?

2 days

3 days

4 days

5 days

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?