Chapter 02 Organizational

Chapter 02 Organizational

University

20 Qs

quiz-placeholder

Similar activities

HLTH 1032 Module 1 Nervous system and sensory

HLTH 1032 Module 1 Nervous system and sensory

University

18 Qs

Destination C1-C2-T20

Destination C1-C2-T20

University

20 Qs

Chương 3 : Values, Attitudes, and job satisfaction

Chương 3 : Values, Attitudes, and job satisfaction

University

15 Qs

Disaster Management

Disaster Management

University

15 Qs

GK Marathon -01 Quiz

GK Marathon -01 Quiz

10th Grade - Professional Development

15 Qs

inclusive education

inclusive education

University

20 Qs

ระเบียบวิธีวิจัย

ระเบียบวิธีวิจัย

University

20 Qs

Kuliah Umum Perpajakan

Kuliah Umum Perpajakan

University - Professional Development

15 Qs

Chapter 02 Organizational

Chapter 02 Organizational

Assessment

Quiz

Special Education

University

Practice Problem

Hard

Created by

Suci Miranda

Used 22+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 5 pts

A hospital is installing a new hospital management system to enable IT hospital functioning. For this purpose, representatives from several departments are selected to create a task force assigned to implement the project. This organization structure is called?

Functional Organization
Projectized Organization
Composite Organization
Balanced Matrix Organization

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is identifying relevant enterprise environmental factors on his project. Which of the following is NOT a valid example?

Organizational Culture and processes
Stakeholder Risk Tolerances
Employee performance Review records
Historical lessons learned knowledge base

3.

MULTIPLE CHOICE QUESTION

2 mins • 5 pts

A project manager is working on constructing a new bridge, but he is not getting enough project attention. Resources are occupied in doing process related work and the project manager has little authority to assign resources. What form of organization is the project being performed?

Functional
Strong Matrix
Projectized
Weak Matrix

4.

MULTIPLE CHOICE QUESTION

2 mins • 5 pts

You are a project manager currently finding all of the risks on the project. As a part of this activity, you would like to know the risk attitude and organization policies and procedures for risk management. Which of the following should you refer for this purpose?

Enterprise and Environmental Factors
Stakeholder Register
Risk Management Plan
Project Documents

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Mansour works for a consulting company that regularly acquires project teams for any new assignments. Once the assignment is over, the team is dissolved. What kind of organization is Mansour working for?

Matrix
Projectized
Functional
Balanced Matrix

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following phase-to-phase relationships reduces uncertainty but may eliminate options for reducing the schedule?

Overlapping relationship
Sequential relationship
Iterative relationship
Continuous relationship

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following regarding risk and cost of changes is true?

Risk and cost of changes are highest at the beginning of the project
Risk is highest and cost of changes is lowest at the beginning of the project
Risk is lowest and cost of changes is highest at the beginning of the project
Risk and cost of changes are lowest at the beginning of the project

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?