1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource
shifting
effectiveness
manipulating
smoothing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If resources are not adequate to meet peak demands, the resulting reschedule is termed
resource-constrained scheduling
time-constrained scheduling
mandatory levelling
mandatory adjustment
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.
physical
technical
resource
schedule
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project engineer has been scheduled to run the product system test at the same time as building a marketing prototype. This is an example of what type of resource constraint?
physical
technical
people
equipment
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project purchasing agent is trying to order the concrete needed to continue the project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?
working captial
people
equipment
materials
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?