7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:

Agree to analogous estimating, as it is a form of expert judgment

Suggest life cycle costing

Determine why the sponsor wants such an accurate estimate

Try to convince the sponsor to allow expert judgment because it is typically more accurate.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are the program level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem?

Regression Analysis

Risk Quantification Reports

Monte Carlo Analysis

Quality Audits

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk management activities. For remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also these 2 risks cannot be outsourced or removed from project scope. What is the best solution?

Mitigate the risk

Accept the risk

Avoid the risk

Transfer the risk

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are managing a software upgrade project for your company. Your project sponsor has a great deal of authority regarding project decisions, but you recently discovered that he doesn't have much interest in your project. To complete the project successfully, you need your project sponsor's continuous support.

What stakeholder management strategy should you use with your project sponsor?

Keep the sponsor satisfied

Manage the sponsor closely

Monitor the sponsor's actions

Keep the sponsor informed

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

John is a project manager of a complicated project. When he started creating a work breakdown structure for his project, he realized that it is too complex to complete work breakdown structure on a single sheet. You, as a colleague of John, recommend using a work breakdown structure numbering system to John to:

Determine the complexity of the project

Help in automating the WBS using appropriate software

Provide a hierarchical structure for each WBS element

Present risks of the project

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which statement describes best the purpose of the communications management plan?

The project management plan is a subsidiary document of the overall communications management plan.

The communications management plan describes rules of behavior and respect for communications in cross-cultural teams.

The communications management plan describes the information delivery needs including format and level of detail.

The communications management plan focuses on the use of communications technologies by the project management team

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When identifying the basis of the business need for a project all of the following can be considered except____,

Regular plant maintenance

Market demands

Technological advances

Legal requirements

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development