
PRM crashing the project duration
Authored by Linh Ngo
Business
University
Used 6+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
9 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year. This may lead to a project that must be done faster than anticipated. This is an example of reducing project duration caused by
Imposed project deadlines
Time to market
Unforeseen project delays
High overhead
Incentive contracts
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
As a project is crashed and project duration is reduced, indirect costs typically
Increase
Become unstable
Decrease
Become unreliable
Stay the same
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500, the crash cost per period is:
$500
$750
$1,500
$13,000
$15,000
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The less steep the cost slope of an activity, the
Less it costs to shorten one time period.
More it costs to shorten one time period.
Smaller the crash time is.
Larger the crash time is.
Cannot be determined by the information given.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Two activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _____ should be crashed first, adding ______ to project cost.
Activity Normal time Normal cost Crash duration Crash cost
One 8 days $6,000 6 days $6,800
Two 10 days $4,000 9 days $5,000
One; $400
One; $6,800
Two; $1,000
Two; $5,000
One or two should be crashed; $1,400
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion. This is an example of reducing project duration caused by
Imposed project deadlines
Unforeseen project delays
Time to market
Incentive contracts
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT considered a project indirect cost?
Supervision
Equipment
The project manager's salary
Consultants
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?