1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for tracking the remaining work of the Sprint?

The Development Team.

The Scrum Master.

The Project Manager.

The Development Team is consultation with the Product Owner.

The Product Owner.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement best describes a Product Owner’s responsibility? (Choose the best answer.)

Optimizing the value of the work the Scrum Team does.

Ensuring that the work meets the commitments to the stakeholders.

Directing the Development Team.

Keep stakeholders from distracting the Development Team.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the role of management in Scrum? (Choose the best answer.)

Add a specialist to the Development Team.

Partially complete the functionality and discuss the remaining work at the Sprint Review.

Collaborate with the Product Owner to determine what is possible and acceptable.

Defer the work to a more appropriate Sprint.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When is the Sprint Backlog created?

At the beginning of the project.

During the Sprint Planning meeting.

Prior to the Sprint Planning meeting.

During the Sprint.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?

Lead the discussions of the Development Team.

Make sure that all 3 questions have been answered by each member of the team.

Keep track of whether each team member has a chance to speak.

Teach the Development Team to keep the Daily Scrum within the 15-minute time-box.

All of the above.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Methods of communication.

The way the Scrum Team does Sprint Planning.

Skills needed to improve the Development Team’s ability to deliver.

Its Definition of Done.

All of the above.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement best describes the Sprint Review?

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

It is a mechanism to control the Development Team’s activities during a Sprint.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?