Wet Systems Quiz1

Wet Systems Quiz1

Professional Development

8 Qs

quiz-placeholder

Similar activities

Interpersonal Skills

Interpersonal Skills

Professional Development

11 Qs

post Test English Camp 2

post Test English Camp 2

Professional Development

10 Qs

Business Networking Care 3 Topic 3.1

Business Networking Care 3 Topic 3.1

Professional Development

10 Qs

Strategy for Implementing Product / Service Customization

Strategy for Implementing Product / Service Customization

Professional Development

10 Qs

What's That Emoji Nursery Rhyme?

What's That Emoji Nursery Rhyme?

Professional Development

10 Qs

HFTSK-Disbursements_Jul2024_Part2

HFTSK-Disbursements_Jul2024_Part2

Professional Development

8 Qs

INTO Artificial Intelligence

INTO Artificial Intelligence

University - Professional Development

10 Qs

Term 1 Reflection

Term 1 Reflection

KG - Professional Development

11 Qs

Wet Systems Quiz1

Wet Systems Quiz1

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Gregory Bartels

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

The functions of the main drain connection and valve are to drain the system_______.

and test the water supply

and keep the piping from freezing

only

and to check anti-freeze solution

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When performing main drain testing, the valve shall be opened and remain open______.

just for a quick second

until the system pressure stabilizes

for 2 seconds

until the needle drops 10 PSI

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Per NFPA requirements, after an impairment, a main drain test shall be performed________.

if there is a concern by the AHJ and requires it for occupancy

any time a valve is closed for more than a week

after a shutdown of over 48 hours or 2 days

any time the control valve is closed and reopened at system riser

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The initial main drain test is critically important to perform and document because_______.

it is the benchmark to compare future test data to

the insurance company requires the test for their records

it proves to the general contractor that the system is live

. it provides the final flush of the system before we finish the job

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Per NFPA 25, a main drain test on a system containing no backflow preventer must be performed at least _______.

weekly

monthly

quarterly

annually

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Per NFPA 13 requirements, fire sprinklers are to be identified by the

Pipe thread size

Piping connection type

Sprinkler Identification Number (SIN)

UL Listing number

Answer explanation

6.2.2* Sprinkler Identification. All sprinklers shall be permanently

marked with one or two English uppercase alphabetic

characters to identify the manufacturer, immediately followed

by three or four numbers, to uniquely identify a sprinkler as to

K-factor (orifice size) or orifice shape, deflector characteristic,

pressure rating, and thermal sensitivity.

7.

FILL IN THE BLANK QUESTION

1 min • 1 pt

Per NFPA 13:For a new fire sprinkler system installation, working plans shall be submitted to the AHJ for approvals_____

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Per NFPA 13, any changes in the fire sprinkler project from the approved working plans require______.

permission from the AHJ

approval from the owner

approval from the NFPA

review from the other trades on the project

Answer explanation

23.1.2 Deviation from approved plans shall require permission

of the authority having jurisdiction.