1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following statement is FALSE about the Contractor’s entitlement to an extension of time (EOT) due to compliance with the Architect’s Instruction under PAM 2006 Form of Contract?

Delay caused by the dispute related to the land border issue between the Employer and the neighboring property owner.

Delay caused by the discrepancy between contract documents and contract drawings.

Opening up for inspection of the works covered up which shows that the works, materials, and goods were not in accordance with the Contract.

Discovery of the antiquities or other valuable objects on-site during the excavation works for lift pit.

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The Final Account under PAM 2018 Form of Contract shall include the following items EXCEPT:


I. Omission of Provisional Sums not expended.

II. Liquidated Damages imposed by the Employer.

III. Omission and substitution of all Prime Cost Sums in the Contract.

IV. The interest payable by either of the parties.

I, III.

II, IV.

II, III.

I, IV.

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The following items are generally included in the interim certificate under PAM 2006 Form of Contract (With Quantities) EXCEPT:

Value of materials on site.

Value of materials off-site.

Value of works properly executed by nominated sub-contractors.

Value of works properly executed by the main contractor.

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following is NOT the variation definition provided under PAM 2018 Form of Contract (With Quantities)?

Changes with regards to the methods of construction.

Changes with regards to the execution of the works in any specific order.

Changes with regards to the execution of the temporary works.

Changes with regards to the working space.

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The following are the recurring activities upon the issuance of the Certificate of Practical Completion (CPC) under PAM 2006 Form of Contract (With Quantities).


I. 5% of the retention sum shall be released to the Contractor.

II. It marks the commencement of the Defects Liability Period.

III. The contractor’s liability to insured ends except for the maintenance coverage during the Defects Liability Period.

IV. Site possession by the Contractor ceased on the day of Certificate of Practical Completion (CPC).

I, II, III.

I, II, IV.

I, III, IV.

II, III, IV.

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

___________________ is an employer’s events for extension of time (EOT) under PAM 2006 Form of Contract (With Quantities).

Civil commotion, strike, or lockout.

Force Majeure.

Exceptionally inclement weather.

Suspension of the works due to non-payment.

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

_______________________ shall be issued by the Architect for the Employer to take possession of the occupied part with the consent of the Contractor at any time before practical completion of the works under PAM 2006 Form of Contract (With Quantities).

Certificate of Non-Completion.

Certificate of Sectional Completion.

Certificate of Partial Completion.

Certificate of Practical Completion.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?