Network Diagram - AON

Authored by Petcharat Limsupreeyarat

Other

University

Used 10+ times

Network Diagram - AON
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the project duration?

15

18

16

14

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the early start (ES) date of Activity E?

5

6

7

13

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the early finish (EF) date of Activity F ?

5

6

7

8

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the late finish (LF) date of Activity D?

16

10

13

10

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the late start (LS) date of Activity B?

3

6

7

10

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the free float of Activity F?

0

1

3

7

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

According to network diagram which applied Critical Path Method (CPM), what is the total float of Activity G?

0

3

7

8

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?