Earned Value Management (EVM)

Earned Value Management (EVM)

University - Professional Development

21 Qs

quiz-placeholder

Similar activities

Chapter 2 : Manufacturing Cost Concept and Components

Chapter 2 : Manufacturing Cost Concept and Components

University - Professional Development

16 Qs

strategic management

strategic management

University

20 Qs

6219-08 City and Guilds Construction Level Quiz

6219-08 City and Guilds Construction Level Quiz

Professional Development

18 Qs

Formal, Informal and Non-Formal Education

Formal, Informal and Non-Formal Education

Professional Development

19 Qs

Applied Project Management

Applied Project Management

Professional Development

20 Qs

WORK VOCABULARY B2

WORK VOCABULARY B2

Professional Development

16 Qs

Hybrid Project Management - Quiz 1 - 11/02/2025

Hybrid Project Management - Quiz 1 - 11/02/2025

University

18 Qs

QUIZ 1 : TOPIC 8 [JOB ORDER COSTING]

QUIZ 1 : TOPIC 8 [JOB ORDER COSTING]

1st Grade - University

20 Qs

Earned Value Management (EVM)

Earned Value Management (EVM)

Assessment

Quiz

Education

University - Professional Development

Hard

Created by

PROFESOR ISA

Used 48+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Earned Value Management & Analysis

is a project control technique preferred by PMI

is used to detect performance variances

is used to establish a clear relationship between planned and actual accomplishments

is a way to forecast project’s cost and completion date using historical and statistical projections.

is a project analysis tools can answer these questions using time and cost tracking

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Being as a project managers there are important elements related to "Earned Value" that you need to know related to the followings:

Is the project on schedule? Time tracking

Is the project on budget? Cost tracking

How much of the budget that should have been spent at this point in time

How much value has the work on the project "earned" so far?

Is the project fulfill the quality? Quality tracking

3.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Select the correct definition and concepts for Earned Value Management

Budgeted Cost of Work Scheduled (BCWS) answers "how much work has been actually completed?"

Budgeted Cost of Work Performed (BCWP) answers "how much work has been actually completed?"

Actual Cost of Work Performed (ACW) how much did we actually spend to deliver the Earned Value? which is the Actual Cost (AC)

Budgeted Cost of Work Performed (BCWP) is the “Earned Value” (EV)

Budgeted Cost of Work Scheduled (BCWS) is “Planned Value" (PV)

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Select the "Earned Value" components below:

Planned Value (PV)

How much work (person-hours) you planned to have accomplished at a given point in time (this is from the WBS in your plan)

Earned Value (EV)

The value (person-hours) in terms of your base budget of what you have at a given point in time (or, % complete X Planned Value)

Actual Cost (AC)

How much work (person-hours) you have actually planned at a given point in time

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In short, EVM takes the planned value (PV), or what you planned to do at an estimated cost, and compares it against the estimated cost of the work performed (EV) and against the actual cost of work performed (AC), or what actually got done.

False

True

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Select the correct information below: (you may choose more than one answer)

Schedule variance (SV) shows whether the project tasks are taking longer than they should

Cost variance (CV) shows whether they are actually requiring more work effort to complete

Estimate-at-completion metric (EAC) helps to forecast final project performance and determine if any corrective action needs to take place

7.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Media Image

This figure shown and example of "Earned Value". Select the correct combination of the three important elements (A, B and C) for earned value analysisi

A: .Planned Value: what your plan called for sending on the tasks planned to be completed by this date.

B: Actual Cost: what you have actually spent to this point in time

C: Earned Value: value (cost) of what you have accomplished to date, per the base plan.

A: Actual Cost: what you have actually spent to this point in time.

B: Planned Value: what your plan called for sending on the tasks planned to be completed by this date.

C: Earned Value: value (cost) of what you have accomplished to date, per the base plan.

A: .Earned Value: value (cost) of what you have accomplished to date, per the base plan.

B: Planned Value: what your plan called for sending on the tasks planned to be completed by this date.

C: Actual Cost: what you have actually spent to this point in time

A: Earned Value: value (cost) of what you have accomplished to date, per the base plan.

B: Actual Cost: what you have actually spent to this point in time

C: .Planned Value: what your plan called for sending on the tasks planned to be completed by this date.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?