Earned Value Management (EVM)

Quiz
•
Education
•
University - Professional Development
•
Hard
PROFESOR ISA
Used 48+ times
FREE Resource
21 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Earned Value Management & Analysis
is a project control technique preferred by PMI
is used to detect performance variances
is used to establish a clear relationship between planned and actual accomplishments
is a way to forecast project’s cost and completion date using historical and statistical projections.
is a project analysis tools can answer these questions using time and cost tracking
2.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Being as a project managers there are important elements related to "Earned Value" that you need to know related to the followings:
Is the project on schedule? Time tracking
Is the project on budget? Cost tracking
How much of the budget that should have been spent at this point in time
How much value has the work on the project "earned" so far?
Is the project fulfill the quality? Quality tracking
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Select the correct definition and concepts for Earned Value Management
Budgeted Cost of Work Scheduled (BCWS) answers "how much work has been actually completed?"
Budgeted Cost of Work Performed (BCWP) answers "how much work has been actually completed?"
Actual Cost of Work Performed (ACW) how much did we actually spend to deliver the Earned Value? which is the Actual Cost (AC)
•Budgeted Cost of Work Performed (BCWP) is the “Earned Value” (EV)
Budgeted Cost of Work Scheduled (BCWS) is “Planned Value" (PV)
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Select the "Earned Value" components below:
Planned Value (PV)
How much work (person-hours) you planned to have accomplished at a given point in time (this is from the WBS in your plan)
Earned Value (EV)
The value (person-hours) in terms of your base budget of what you have at a given point in time (or, % complete X Planned Value)
Actual Cost (AC)
How much work (person-hours) you have actually planned at a given point in time
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In short, EVM takes the planned value (PV), or what you planned to do at an estimated cost, and compares it against the estimated cost of the work performed (EV) and against the actual cost of work performed (AC), or what actually got done.
False
True
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Select the correct information below: (you may choose more than one answer)
Schedule variance (SV) shows whether the project tasks are taking longer than they should
Cost variance (CV) shows whether they are actually requiring more work effort to complete
Estimate-at-completion metric (EAC) helps to forecast final project performance and determine if any corrective action needs to take place
7.
MULTIPLE SELECT QUESTION
1 min • 1 pt
This figure shown and example of "Earned Value". Select the correct combination of the three important elements (A, B and C) for earned value analysisi
A: .Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
B: Actual Cost: what you have actually spent to this point in time
C: Earned Value: value (cost) of what you have accomplished to date, per the base plan.
A: Actual Cost: what you have actually spent to this point in time.
B: Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
C: Earned Value: value (cost) of what you have accomplished to date, per the base plan.
A: .Earned Value: value (cost) of what you have accomplished to date, per the base plan.
B: Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
C: Actual Cost: what you have actually spent to this point in time
A: Earned Value: value (cost) of what you have accomplished to date, per the base plan.
B: Actual Cost: what you have actually spent to this point in time
C: .Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
Create a free account and access millions of resources
Similar Resources on Wayground
18 questions
6219-08 City and Guilds Construction Level Quiz

Quiz
•
Professional Development
19 questions
Formal, Informal and Non-Formal Education

Quiz
•
Professional Development
20 questions
Strategic Logistic Plan

Quiz
•
Professional Development
20 questions
Applied Project Management

Quiz
•
Professional Development
20 questions
QUIZ 1 : TOPIC 8 [JOB ORDER COSTING]

Quiz
•
1st Grade - University
20 questions
REVISION 4 : TOPIC 9 [ACCOUNTING FOR NON-CURRENT ASSETS]

Quiz
•
1st Grade - University
20 questions
KUIS INDIVIDU MATERI BMC

Quiz
•
University
20 questions
strategic management

Quiz
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade