Earned Value Management & Analysis
Earned Value Management (EVM)

Quiz
•
Education
•
University - Professional Development
•
Hard
PROFESOR ISA
Used 48+ times
FREE Resource
21 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
1 min • 1 pt
is a project control technique preferred by PMI
is used to detect performance variances
is used to establish a clear relationship between planned and actual accomplishments
is a way to forecast project’s cost and completion date using historical and statistical projections.
is a project analysis tools can answer these questions using time and cost tracking
2.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Being as a project managers there are important elements related to "Earned Value" that you need to know related to the followings:
Is the project on schedule? Time tracking
Is the project on budget? Cost tracking
How much of the budget that should have been spent at this point in time
How much value has the work on the project "earned" so far?
Is the project fulfill the quality? Quality tracking
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Select the correct definition and concepts for Earned Value Management
Budgeted Cost of Work Scheduled (BCWS) answers "how much work has been actually completed?"
Budgeted Cost of Work Performed (BCWP) answers "how much work has been actually completed?"
Actual Cost of Work Performed (ACW) how much did we actually spend to deliver the Earned Value? which is the Actual Cost (AC)
•Budgeted Cost of Work Performed (BCWP) is the “Earned Value” (EV)
Budgeted Cost of Work Scheduled (BCWS) is “Planned Value" (PV)
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Select the "Earned Value" components below:
Planned Value (PV)
How much work (person-hours) you planned to have accomplished at a given point in time (this is from the WBS in your plan)
Earned Value (EV)
The value (person-hours) in terms of your base budget of what you have at a given point in time (or, % complete X Planned Value)
Actual Cost (AC)
How much work (person-hours) you have actually planned at a given point in time
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In short, EVM takes the planned value (PV), or what you planned to do at an estimated cost, and compares it against the estimated cost of the work performed (EV) and against the actual cost of work performed (AC), or what actually got done.
False
True
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Select the correct information below: (you may choose more than one answer)
Schedule variance (SV) shows whether the project tasks are taking longer than they should
Cost variance (CV) shows whether they are actually requiring more work effort to complete
Estimate-at-completion metric (EAC) helps to forecast final project performance and determine if any corrective action needs to take place
7.
MULTIPLE SELECT QUESTION
1 min • 1 pt
This figure shown and example of "Earned Value". Select the correct combination of the three important elements (A, B and C) for earned value analysisi
A: .Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
B: Actual Cost: what you have actually spent to this point in time
C: Earned Value: value (cost) of what you have accomplished to date, per the base plan.
A: Actual Cost: what you have actually spent to this point in time.
B: Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
C: Earned Value: value (cost) of what you have accomplished to date, per the base plan.
A: .Earned Value: value (cost) of what you have accomplished to date, per the base plan.
B: Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
C: Actual Cost: what you have actually spent to this point in time
A: Earned Value: value (cost) of what you have accomplished to date, per the base plan.
B: Actual Cost: what you have actually spent to this point in time
C: .Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
Create a free account and access millions of resources
Similar Resources on Quizizz
21 questions
IFRS ENG Test 3

Quiz
•
University
20 questions
COSTA RICA CORE PRACTICE

Quiz
•
Professional Development
20 questions
SMALL TEST AKM 1 - WEEK 3

Quiz
•
University
17 questions
International Trade

Quiz
•
University
20 questions
GERUNDS, INFINITIVES AND PARTICIPLES

Quiz
•
Professional Development
20 questions
Genel Kültür Quiz

Quiz
•
University
24 questions
TQ1-CHAPTER 4 : INVENTORY

Quiz
•
University
20 questions
Supply_PKT Cycle 1_July'23

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade