Applied Project Management

Applied Project Management

Professional Development

20 Qs

quiz-placeholder

Similar activities

HKMNOP C2

HKMNOP C2

University - Professional Development

20 Qs

IDU Learning Approaches

IDU Learning Approaches

Professional Development

15 Qs

Chapter 2 : Manufacturing Cost Concept and Components

Chapter 2 : Manufacturing Cost Concept and Components

University - Professional Development

16 Qs

Am I a leader or a manager?

Am I a leader or a manager?

Professional Development

15 Qs

6219-08 City and Guilds Construction Level Quiz

6219-08 City and Guilds Construction Level Quiz

Professional Development

18 Qs

Business Finance - Quiz #2

Business Finance - Quiz #2

Professional Development

15 Qs

BASIC EDUCATION RESEARCH AGENDA

BASIC EDUCATION RESEARCH AGENDA

Professional Development

15 Qs

Pembelajaran Ms Project

Pembelajaran Ms Project

Professional Development

15 Qs

Applied Project Management

Applied Project Management

Assessment

Quiz

Education

Professional Development

Hard

Created by

Avenew Learning

Used 11+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

While preparing a project's third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track. What should the project manage

Contact the procurement manager to expedite delivery of the material.

Add it to the issue log and include it in the project report.

Discuss it with the project team to determine the most appropriate way to respond.

Escalate the issue to the project owner and request a schedule change

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

George is managing a construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the SS (Start to Start) and FF (Finish to Finish) relationships. How should George schedule these activities?

Select the FF relationship as this can help meet the project deadlines

Select the relationship with the highest impact

Apply both the relationships

Select the SS relationship as this is more logical than the FF relationship

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have just received an invoice from your supplier that contains some uncertified items. Payments to the supplier are processed through your corporate accounts payable system only after certification of satisfactory work by the project quality control specialist. What should you do?

Ask the supplier to stop all deliveries until the matter has a resolution

Process the supplier’s invoice since this is your liability

Call the supplier and obtain more information

Seek judicial arbitration

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are managing a track construction project. The construction contract awarded to your company is fixed price and is based on some pre-determined quantities of work to be executed. During the project execution you find out that the actual quantities of work that need to be executed are 20% greater than what has been stated in the contract. What should you do?

Engage a third-party arbitrator to help resolve the issue

Bill the buyer the additional scope of work separately without amending the contract

Sue the buyer for stating wrong quantities in the contract

Collect necessary evidence and request the buyer to amend the contract with new quantities

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A functional manager meets with the project manager's boss to discuss a change to the acceptance criteria for a major deliverable. After the meeting, the boss calls the project manager into his office and tells him to make the change. What is the BEST thing to do?

Make the change as soon as possible

Update the baseline with the instructed changes

Evaluate the impact of the change

Supply the boss with a change form

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Ben is the project manager for a mobile application development project. Due to a recent technological development, a significant change in the product design is required. This change would require a 25 percent increase in the project budget. Ben prepares a detailed report and emails it to the project sponsor, and the sponsor acknowledges the receipt of the report. What should Ben do next?

Update the cost management plan

Update the project budget

Update the project schedule

Wait for the formal approval of the new budget

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A complex project is in the planning phase. The sponsor assigns a newly certified project manager to the project. Upon review of the project charter, the project manager uncovers several factors that could impact the project in unpredictable ways. What should the project manager do?

Inform the project sponsor about the possible impacts these factors may have on the project

Update the project plan with details about schedule and budget forecasts

Extend the issue log to include a what-if scenario analysis

Develop a risk management plan with details about the various factors

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?