While preparing a project's third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track. What should the project manage
Applied Project Management

Quiz
•
Education
•
Professional Development
•
Hard
Avenew Learning
Used 11+ times
FREE Resource
20 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Contact the procurement manager to expedite delivery of the material.
Add it to the issue log and include it in the project report.
Discuss it with the project team to determine the most appropriate way to respond.
Escalate the issue to the project owner and request a schedule change
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
George is managing a construction project and currently sequencing the project activities and defining their logical relationships. Two activities have both the SS (Start to Start) and FF (Finish to Finish) relationships. How should George schedule these activities?
Select the FF relationship as this can help meet the project deadlines
Select the relationship with the highest impact
Apply both the relationships
Select the SS relationship as this is more logical than the FF relationship
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have just received an invoice from your supplier that contains some uncertified items. Payments to the supplier are processed through your corporate accounts payable system only after certification of satisfactory work by the project quality control specialist. What should you do?
Ask the supplier to stop all deliveries until the matter has a resolution
Process the supplier’s invoice since this is your liability
Call the supplier and obtain more information
Seek judicial arbitration
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are managing a track construction project. The construction contract awarded to your company is fixed price and is based on some pre-determined quantities of work to be executed. During the project execution you find out that the actual quantities of work that need to be executed are 20% greater than what has been stated in the contract. What should you do?
Engage a third-party arbitrator to help resolve the issue
Bill the buyer the additional scope of work separately without amending the contract
Sue the buyer for stating wrong quantities in the contract
Collect necessary evidence and request the buyer to amend the contract with new quantities
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A functional manager meets with the project manager's boss to discuss a change to the acceptance criteria for a major deliverable. After the meeting, the boss calls the project manager into his office and tells him to make the change. What is the BEST thing to do?
Make the change as soon as possible
Update the baseline with the instructed changes
Evaluate the impact of the change
Supply the boss with a change form
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Ben is the project manager for a mobile application development project. Due to a recent technological development, a significant change in the product design is required. This change would require a 25 percent increase in the project budget. Ben prepares a detailed report and emails it to the project sponsor, and the sponsor acknowledges the receipt of the report. What should Ben do next?
Update the cost management plan
Update the project budget
Update the project schedule
Wait for the formal approval of the new budget
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A complex project is in the planning phase. The sponsor assigns a newly certified project manager to the project. Upon review of the project charter, the project manager uncovers several factors that could impact the project in unpredictable ways. What should the project manager do?
Inform the project sponsor about the possible impacts these factors may have on the project
Update the project plan with details about schedule and budget forecasts
Extend the issue log to include a what-if scenario analysis
Develop a risk management plan with details about the various factors
Create a free account and access millions of resources
Similar Resources on Quizizz
20 questions
Unit 207 - Develop and Maintain Session Recap

Quiz
•
Professional Development
15 questions
THINKING OUT OF THE BOX PRETEST

Quiz
•
Professional Development
15 questions
Diplomado Intec - Ágil

Quiz
•
Professional Development
15 questions
BIMT

Quiz
•
Professional Development
20 questions
Training ISO 45001 SP09-SP16

Quiz
•
Professional Development
20 questions
Topic 5 Ethics and Professionalism

Quiz
•
Professional Development
20 questions
Quiz - Referenti BIM 2024

Quiz
•
Professional Development
20 questions
Cobit2019 Post-Test

Quiz
•
University - Professi...
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade