Search Header Logo

PMP Exam Study Group - Chapter 6 Schedule

Authored by quiz eNetwoQ

Education

KG

Used 18+ times

PMP Exam Study Group - Chapter 6 Schedule
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project manager is in the middle of executing a project when they discover the project is behind schedule. The project deadline cannot be extended, and the project sponsor will not approve any scope or budget changes. Which of the following is the best course of action for the project manager to take to complete the project faster?

Hire additional resources and work overtime

Tell the sponsor that the deadline cannot be met

Look at options for fast tracking the critical path

Level the resources

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

To create the project schedule, a project manager needs to break down the project scope and develop a comprehensive list of activities, which are needed to complete the deliverable. What tool or technique should project manager use in this situation?

Work breakdown structure

Decomposition

Progressive elaboration

Gold plating

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

An agile team is using a Kanban board to track their work. There is still quite a bit of work to be done, which was why a new tester was added to the team. The new tester overheard comments from others about too much work in process (WIP) on their Kanban board. Which of the following is considered an example of WIP?

User stories that contain code that is waiting for customer feedback

User stories that have yet to be prioritized by the product owner

User stories that are awaiting selection by the team

Deployed user stories that contain code that has already been integrated

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Following are the activities and durations on a project schedule. The project is in planning. If activities C, D and F are on the critical path, what is the total float for activity D?

4 days

7 days

0 Days

Cannot be determined

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

According to the industry's generally accepted best practices, the electrical work on the appliances assembly line should be completed prior to installing the doors.

What does this sequence of activities represent?

Activity attributes

Discretionary dependencies

Activity list

Mandatory dependencies

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You have just completed the Develop Schedule process and you are now preparing information for the project sponsor to highlight the activities that may create a delay in the overall project schedule. Which of the following would be most useful in this situation?

Activity attributes

Project network diagrams

Duration estimates

Project calendars

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project manager had originally planned to use two industrial 3D printers simultaneously for a project but has just learned that one of them will be unavailable. The project manager adjusts the schedule so that the components are created sequentially using one printer. Unfortunately, this action affects the critical path and delays the planned finish date of the project. What tool or technique has the project manager used in this situation?

Fast tracking

Resource smoothing

Crashing

Resource leveling

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?