PMP Exam - Study Group Ch Quality and Resources

PMP Exam - Study Group Ch Quality and Resources

KG

10 Qs

quiz-placeholder

Similar activities

PMP Exam Preparation - Ch Communication and Stakeholder

PMP Exam Preparation - Ch Communication and Stakeholder

KG

10 Qs

PMP SG Ch 6 Schedule Post Test

PMP SG Ch 6 Schedule Post Test

KG

10 Qs

PMI ACP Domain 7 Continuous Improvement

PMI ACP Domain 7 Continuous Improvement

KG

10 Qs

Scrum & Agile

Scrum & Agile

University

11 Qs

SAFe for Teams - Lesson 1

SAFe for Teams - Lesson 1

Professional Development

12 Qs

Study Group PMP Chapter 4  Project Integration Management

Study Group PMP Chapter 4 Project Integration Management

KG

10 Qs

PBS - Segunda Revisión

PBS - Segunda Revisión

University

10 Qs

PMP Exam Preparation Mentoring - Agile Session

PMP Exam Preparation Mentoring - Agile Session

KG

10 Qs

PMP Exam - Study Group Ch Quality and Resources

PMP Exam - Study Group Ch Quality and Resources

Assessment

Quiz

Education

KG

Hard

Created by

quiz eNetwoQ

Used 9+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

1. Development team members argue with the product owner who rejected a deliverable the team developed during the recent iteration. The project manager schedules a meeting with the team, product owner, and other relevant stakeholders to breakdown the situation and identify the root cause of a misunderstanding.

Which of the following will be considered an antipattern if used during the meeting?

A. Drawing a fishbone diagram

B.Using the five whys method

C. Maximizing the number of action items

D. Defining the problem statement

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

2. As a project manager, you are leading a colocated project team that will create deliverables in an agile fashion, followed by a rollout phase that will use a predictive approach. You are concerned that the transition from agile to waterfall may cause friction within the project team.

With the development phase complete, how might the team's working agreements need to change in this situation?

A. The team charter will need to be updated to reflect collective responsibility for the completion of project tasks

B. The project manager should institute a set of working agreements that worked well on previous waterfall<br />projects.

C. Each project team member will need to develop their own social contract to support the new framework.

D. The social contract should reflect a transition from collective to individual responsibility for the project tasks.

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

3. At the sprint planning meeting, the scrum master reiterates that if by the end of the sprint the product increment that the agile project team is building does not meet the criteria specified at the beginning of the sprint, this work will not be included in the velocity for the current sprint.

What does the scrum master refer to?

A. Estimate to complete

B. Definition of done

C. Project exit criteria

D. Quality metrics

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

4. You are managing a virtual project team across multiple time zones. As the project progresses, the team members learn to trust one another and adjust their work routines to accommodate the different time zones, work habits, and culture.

What stage of team development is being demonstrated in this situation?

A.Forming

B. Storming

C. Performing

D. Norming

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

5. An agile team has just completed the development of the final project's deliverable. The team members are seeking advice from the project manager as to their next step.

What should the project manager advise the team to do next?

A. Determine the acceptance criteria

B. Ensure that the user stories meet the definition of ready (DoR)

C. Hold a project retrospective

D. Verify that the deliverables meet the definition of done (DoD)

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

6. As a scrum master, you are facilitating a retrospective for a sprint that failed to meet all of its objectives. Members of the development team and the product owner are arguing over who is responsible for the failure. After performing a root cause analysis, you uncover the source of the conflict.

Of the following, what did you most likely discover?

A. The product owner determined how many user stories were to be completed during the sprint

B. The development team decided how many user stories were to be completed during the sprint

C. You, as the scrum master, failed to assign user stories to the development team

D. The Gantt chart did not include enough story points

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

7. A project manager schedules a meeting for the scrum project team to reflect and adapt.

What will the participants be most likely doing at this meeting?

A. Demonstrating the product increment to the customer

B. Selecting user stories for the next sprint

C. Discussing the on-going work and impediments to progress

D. Looking for any improvements to the team's process

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?