Project Controls PC 09 Rev 04

Project Controls PC 09 Rev 04

1st Grade

8 Qs

quiz-placeholder

Similar activities

Wealth 101

Wealth 101

1st - 5th Grade

10 Qs

20180706 Quiz SOP

20180706 Quiz SOP

1st - 3rd Grade

10 Qs

PA01 PA Setups

PA01 PA Setups

1st Grade

8 Qs

On-boarding Program Pt II

On-boarding Program Pt II

1st - 3rd Grade

10 Qs

Chapt4

Chapt4

1st Grade

10 Qs

11. Risk Management

11. Risk Management

1st - 3rd Grade

12 Qs

12. Procurement Management

12. Procurement Management

1st - 3rd Grade

12 Qs

OPM_1

OPM_1

1st - 5th Grade

8 Qs

Project Controls PC 09 Rev 04

Project Controls PC 09 Rev 04

Assessment

Quiz

Professional Development

1st Grade

Easy

Created by

Gary Carr

Used 10+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

People and Labour are usually recognised as what type of project spend?

CAPEX

OPEX

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Plant & Equipment are usually accepted as CAPEX items?

True

False

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Who can authorise the use of Management Reserves?

Project Manager

CEO

Cost Engineer

None of the options listed

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is a term used for Money associated to complete specific phases of a project ?

Purchase Order

Contingency

Allowance

Baseline

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A tax that all limited companies must pay and it's a tax that's payable against the profits a company makes is called what?

VAT

Corporate Tax

Income Tax

Import Duty

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Work Packages are linked to which process

Change Control

Risk

WBS

Assumptions

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Network Path shown having zero float is called what?

Zero Path

Total Float

Critical Path

Critical Cover

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Work Packages grouped together can be given the term Control accounts?

True

False