1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Well intervention can be carried out in:
live wells only
dead wells only
both live and dead wells
none of the answer
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which wireline operation allows real-time recording of pressure and temperature?
E-line
Slickline
E-line and slickline
E-line, slickline and braided line
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following well problem cannot be performed using slickline operation?
installation of gas lift valve
shifting slide door sleeves
sand bailing and debris
cementing
Answer explanation
Cementing requires pumping of fluids into the well. Slickline does not allow pumping fluids. This can only be done using direct pumping unit, coiled tubing unit and hydraulic workover unit
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following operation has to be carried out using hydraulic workover?
wellbore cleanout
fishing
setting plug
replacement of production tubing
Answer explanation
Slickline unit and coiled tubing unit only able to conduct light well intervention. Heavy well intervention such as pulling out of production tubing and casing have to be carried out using hydraulic workover.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The following diagram represents the reservoir performance. A production gap exists as reservoir do not effectively deliver hydrocarbon into a wellbore. Which of the following does not help to improve the situation?
perforation
acidising and fracturing
isolate the high water cut formation zone
remove scale in the production tubing
Answer explanation
The result of reservoir performance is low flow rates at high-drawdown pressures. The problem may be overcome by focusing solution at the reservoir and IPR curve.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The graph focuses on flow-conduit performance. Which of the following can help to improve the flow-conduit performance?
coiled tubing completion
remove restrictions in the production tubing
clean out the debris in the tubing
all of the mentioned
Answer explanation
If tubulars are improperly sized and if there are unnecessary mechanical restrictions such as scale buildups inside the tubing and casing.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is the primary well barrier of slickline operation?
BOP
stuffing box
downhole safety valve
drilling mud
Answer explanation
Primary well barrier - stuffing box (slickline operation can perform in live well. Stuffing box is activated to seal the well pressure.
Secondary well barrier - BOP. Only activated when primary well barrier fails or powerpack failure or other emergency situation.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?