1.

MULTIPLE CHOICE QUESTION

1 min • Ungraded

You are a project manager at a new start-up company that specializes in programming for the hot online Gaming industry.  The team is bright and energetic however have little project experience.  They are struggling to keep scope under control and lack understanding between project scope and product scope.  Consider the scope examples below and identify if they fall into the product category.  

Graphical design

Testing

25 Games levels in 1st release

Apple/PC/Andriod Compatibility

Code development and programming

2.

MULTIPLE CHOICE QUESTION

1 min • Ungraded

You are a project manager at a new start-up company that specializes in programming for the hot online Gaming industry.  The team is bright and energetic however have little project experience.  They are struggling to keep scope under control and lack understanding between project scope and product scope.  Consider the scope examples below and identify if they fall into the project category.  

8 game characters

Monitoring & Controlling

25 Game levels in 1st release

Apple/PC/Andriod Compatibility

Code development and programming

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Select the option that best describes Product Scope:

A statement describing the behaviour and expectations of the product

A summary of what the project is intended to accomplish

All the work involved to make or delivery the product/service

The features and functions of the product or service

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Select the option that best describes Project Scope:

A summary of what the project is intended to accomplish

A statement describing the behaviour and expectations of the product

The features and functions of the product or service

All the work involved to make or delivery the product/service

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Select the option that best describes Scope Creep:

Scope changes that cause the schedule to be delayed

A statement describing the behaviour and expectations of the product

Undocumented changes or increases to project or product scope

Uncontrolled changes or increases to project or product scope

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Identify the PMBOK processes the Scope Management Knowledge Area fall within (select all that apply)

Closing Process Group

Monitoring and Controlling Process Group

Initiating Process Group

Planning Process Group

Executing Process Group

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Verify requirements is one of the 6 scope management processes

True

False

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?