Testing and decommissioning of domestic hot water systems

Quiz
•
Other
•
Professional Development
•
Medium

Martin Biron
Used 45+ times
FREE Resource
22 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Soundness Testing of Rigid Pipework (Copper and Steel). Select the correct pocess.
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 60 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 1.5 times the working pressure (if system works at 3bar it should be tested at 4.5bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 30 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 2.5 times the working pressure (if system works at 3bar it should be tested at 4.5bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 30 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 1.5 times the working pressure (if system works at 3bar it should be tested at 4.5bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 30 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 1.5 times the working pressure (if system works at 3bar it should be tested at 4.0bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Soundness testing
Before soundness testing, always walk around the system to make sure all joints have been made – visual check:
•Read MI
•Soldered joints made
•Open Compression joints
•Clips are in place
•Check for Open ends
•Soldered joints made
•Compression joints tight
•Clips are in place
•Open ends are open
•Soldered joints made
•Compression joints tight
•Clips are in place
•Open ends
•Soldered joints made
•Compression joints tight
•Clips are removed
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Place in the correct order.
Final Check
Set up equipment
Visual Inspection
Test Period
Complete-Documentation
Complete-Documentation
Test Period
Visual Inspection
Set up equipment
Final Check
Set up equipment
Visual Inspection
Test Period
Final Check
Complete-Documentation
Visual Inspection
Set up Equipment
Test Period
Final Check
Complet-Documentation
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Select the correct soundness test process for Plastic Pipe (Polybutylene)
Test A
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 1.5 times working pressure for 30 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 45 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 1.5 times working pressure for 15 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 45 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 1.5 times working pressure for 30 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 45 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 2.0 times working pressure for 15 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 60 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Select the correct process for Soundness Testing Plastic Pipe (Polybutylene)
Test B
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 30 minutes
•Leave for a further 120 minutes
•Inspect for pressure loss
•If total loss is less than 0.5bar, soundness is good
•You do not want to damage the plastic pipe or O rings
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 45 minutes
•Leave for a further 60 minutes
•Inspect for pressure loss
•If total loss is less than 0.1bar, soundness is good
•You do not want to damage the plastic pipe or O rings
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 30 minutes
•Leave for a further 60 minutes
•Inspect for pressure loss
•If total loss is less than 0.2bar, soundness is good
•You do not want to damage the plastic pipe or O rings
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 30 minutes
•Leave for a further 120 minutes
•Inspect for pressure loss
•If total loss is less than 0.2bar, soundness is good
•You do not want to damage the plastic pipe or O rings
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Add disinfectant to a system (sodium hypochlorite solution or chlorine) for 1 hour
as prescribed in which, British Standard?
BS1010 part 2
BS6700
BS EN 1175
BS EN 6800
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is shown in the photo?
Hydraulic Gas Boiler Test Equipment
Flue Pressure Tester
Hydraulic Pipe Pressure Tester
Hydraulic Drain equipment
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Cardiac / Neurological Emergencies

Quiz
•
University - Professi...
20 questions
CPL Acft Tech - Carburation

Quiz
•
Professional Development
21 questions
Revision Fluid Mechanics

Quiz
•
Professional Development
20 questions
HVAC Advanced Diagnosis (LV3)

Quiz
•
Professional Development
20 questions
A320 CEO PH 7 Refresh

Quiz
•
Professional Development
25 questions
2018 Mechanical Chapter 12

Quiz
•
Professional Development
20 questions
Teller Quiz

Quiz
•
Professional Development
20 questions
Medical Terminology and Definitions

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade