•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 60 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 1.5 times the working pressure (if system works at 3bar it should be tested at 4.5bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 30 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 2.5 times the working pressure (if system works at 3bar it should be tested at 4.5bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 30 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 1.5 times the working pressure (if system works at 3bar it should be tested at 4.5bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
•Slowly fill the system with water
•Walk around system and check for leaks
•Leave to stand for 30 minutes (temperature stabilisation)
•Attach the hydraulic test bucket
•Pump system up to 1.5 times the working pressure (if system works at 3bar it should be tested at 4.0bar etc)
•Leave for one hour
•Check for any pressure drop (no drop allowed)
•Rectify and re-test if necessary
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Soundness testing
Before soundness testing, always walk around the system to make sure all joints have been made – visual check:
•Read MI
•Soldered joints made
•Open Compression joints
•Clips are in place
•Check for Open ends
•Soldered joints made
•Compression joints tight
•Clips are in place
•Open ends are open
•Soldered joints made
•Compression joints tight
•Clips are in place
•Open ends
•Soldered joints made
•Compression joints tight
•Clips are removed
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Place in the correct order.
Final Check
Set up equipment
Visual Inspection
Test Period
Complete-Documentation
Complete-Documentation
Test Period
Visual Inspection
Set up equipment
Final Check
Set up equipment
Visual Inspection
Test Period
Final Check
Complete-Documentation
Visual Inspection
Set up Equipment
Test Period
Final Check
Complet-Documentation
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Select the correct soundness test process for Plastic Pipe (Polybutylene)
Test A
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 1.5 times working pressure for 30 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 45 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 1.5 times working pressure for 15 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 45 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 1.5 times working pressure for 30 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 45 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to 1bar; after 45 minutes check for loss of pressure
•Increase pressure to 2.0 times working pressure for 15 minutes
•Check for pressure loss
•Reduce pressure to one-third for a further 60 minutes
•Check for pressure loss
•You do not want to damage the plastic pipe or O rings.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Select the correct process for Soundness Testing Plastic Pipe (Polybutylene)
Test B
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 30 minutes
•Leave for a further 120 minutes
•Inspect for pressure loss
•If total loss is less than 0.5bar, soundness is good
•You do not want to damage the plastic pipe or O rings
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 45 minutes
•Leave for a further 60 minutes
•Inspect for pressure loss
•If total loss is less than 0.1bar, soundness is good
•You do not want to damage the plastic pipe or O rings
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 30 minutes
•Leave for a further 60 minutes
•Inspect for pressure loss
•If total loss is less than 0.2bar, soundness is good
•You do not want to damage the plastic pipe or O rings
•Slowly fill the system with water
•Walk around system and check for leaks
•Pump system to manufacturer’s test pressure
•Inspect the pressure loss after 30 minutes
•Leave for a further 120 minutes
•Inspect for pressure loss
•If total loss is less than 0.2bar, soundness is good
•You do not want to damage the plastic pipe or O rings
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Add disinfectant to a system (sodium hypochlorite solution or chlorine) for 1 hour
as prescribed in which, British Standard?
BS1010 part 2
BS6700
BS EN 1175
BS EN 6800
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is shown in the photo?
Hydraulic Gas Boiler Test Equipment
Flue Pressure Tester
Hydraulic Pipe Pressure Tester
Hydraulic Drain equipment
Create a free account and access millions of resources
Similar Resources on Quizizz
20 questions
ระบบ PLC Panel (Recycle Water System)

Quiz
•
Professional Development
19 questions
First Aid: Soft Tissue Injuries--10-4

Quiz
•
9th Grade - Professio...
20 questions
M11 Cat A Instruments

Quiz
•
Professional Development
20 questions
Wellness Quiz

Quiz
•
Professional Development
20 questions
Cardiac / Neurological Emergencies

Quiz
•
University - Professi...
21 questions
Revision Fluid Mechanics

Quiz
•
Professional Development
20 questions
CPL Acft Tech - Lubrication & cooling systems

Quiz
•
Professional Development
20 questions
Maintenance quiz

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade