Section 4- Project Integration Management

Quiz
•
Philosophy
•
University
•
Hard
Gal Yamay
Used 25+ times
FREE Resource
19 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
48.Which of the following processes is included in Project Integration Management?
A. Develop project management plan.
B. Control scope definition.
C. Review scope validation.
D. Conduct procurement surveillance.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
49. All of the following are characteristics of the project charter EXCEPT :
A. It formally authorizes the existence of a project.
B. Projects are initiated by an entity external to the project. The project initiator or sponsor should be at the level that is appropriate to procure funding and commit resources to the project.
C. It is used primarily to request bids for a project or a specific phase of a project.
D. It provides the project manager with the authority to apply organizational resources to project activities.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
50.All of the following are characteristics of the Project Management Information System (PMIS) EXCEPT :
A. Automated gathering and reporting on key performance indicators (KPIs) can be part of this system.
B. It provides access to information technology (IT) software tools, such as scheduling soft ware tools, work authorization systems, and configuration management systems.
C. It is used as part of the Direct and Manage Project Work.
D. It is used by the project manager and the project management team primarily to generate presentations to key stakeholders.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
51.Which of the following is NOT true about tools and techniques of Perform Integrated Change Control?
A. They include expert judgment.
B. They include change control meetings.
C. A change control board (CCB) is responsible for meeting and reviewing the change requests and approving, rejecting, or other disposition of those changes.
D. They include project plan updates.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
52. You are managing a $10 million project . Which of the following is an acceptable cause for "re-baselining" this project?
A. The client has approved an addition to the scope of the project with a $150,000 budget increase and a two-week extension of the scheduled completion.
B. The contractor’s company has instituted a quality assurance program in which it has pledged to spend $1 million during the next year.
C. The productivity in the design department is lower than estimated, which has resulted in1,000 additional hours over what was budgeted and a forecasted two-week delay of the scheduled completion.
D. The engineering department of the performing organization has converted to a new $250,000 CAD system.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
53. Configuration management is focused on :
A. The identification and correction of problems arising in functional areas of project implementation.
B. The specification of both the deliverables and the processes, while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.
C. Testing new systems.
D. Identifying, documenting, and controlling changes to the project and the product baselines, while change control is focused on the specifications of both the deliverables and the processes .
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
53. A change control board (CCB) is
A.A formally chartered group of stakeholders responsible for ensuring that only a minimal amount of changes occurs on the project.
B.A formal or an informal group of stakeholders that has oversight of project execution.
C.A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.
D.A dashboard that provides integrated information to help control changes to cost, schedule, and specifications throughout the life of the project
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Philosophies of Education

Quiz
•
University
14 questions
Understanding The Self Lesson 2

Quiz
•
University
20 questions
SF Documentation and Recording Q#2

Quiz
•
University
20 questions
Dasara and Mahabharata

Quiz
•
3rd Grade - University
20 questions
Welcome to Marketing Quiz

Quiz
•
University - Professi...
20 questions
UNDERSTANDING THE SELF

Quiz
•
University
18 questions
GE2 Quiz

Quiz
•
University
17 questions
Philosophies of education Idealism

Quiz
•
University
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade
Discover more resources for Philosophy
10 questions
Would you rather...

Quiz
•
KG - University
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)

Quiz
•
8th Grade - University
7 questions
Force and Motion

Interactive video
•
4th Grade - University
10 questions
The Constitution, the Articles, and Federalism Crash Course US History

Interactive video
•
11th Grade - University
7 questions
Figurative Language: Idioms, Similes, and Metaphors

Interactive video
•
4th Grade - University
20 questions
Levels of Measurements

Quiz
•
11th Grade - University
16 questions
Water Modeling Activity

Lesson
•
11th Grade - University
10 questions
ACT English prep

Quiz
•
9th Grade - University