Project Controls PC 07 Rev 01

Project Controls PC 07 Rev 01

1st Grade

15 Qs

quiz-placeholder

Similar activities

PMI SH Plan and Manage Scope

PMI SH Plan and Manage Scope

1st Grade

10 Qs

03. Chapter123_PM  Framework

03. Chapter123_PM Framework

1st Grade

12 Qs

RMP - 2. STRATEGY & PLANNING

RMP - 2. STRATEGY & PLANNING

1st Grade

16 Qs

PMI SH - Evaluate and Deliver Project Benefits and Value

PMI SH - Evaluate and Deliver Project Benefits and Value

1st Grade

18 Qs

PMI-SH Plan and Manage Quality of Products/deliverables

PMI-SH Plan and Manage Quality of Products/deliverables

1st Grade

13 Qs

07. Cost Management

07. Cost Management

1st - 3rd Grade

12 Qs

ITPM Pre-Test & Post-Test

ITPM Pre-Test & Post-Test

1st - 5th Grade

20 Qs

PMI SH Manage Project Issues

PMI SH Manage Project Issues

1st Grade

12 Qs

Project Controls PC 07 Rev 01

Project Controls PC 07 Rev 01

Assessment

Quiz

Professional Development

1st Grade

Medium

Created by

Gary Carr

Used 11+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project schedule is the essential map used for the successful --------- of a project.

Initiation

Planning

Execution

Closing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is the Project Charter an Input to the Plan Schedule Process?

Yes

No

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The Plan Schedule Process has one Output, which answer is the correct option?

The Schedule Baseline

The Resource Calendars

The Schedule Management Plan

The WBS

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

From the Inputs utilised for the Plan Schedule Management Knowledge area,which Tools and Techniques would you employ to create specific information to publish the initial Schedule Management Plan as an Output

Expert Judgement

Data Analysis

Meetings

All Options Listed.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work breakdown structure (WBS) provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules.

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Information within the Schedule Management Plan would include the Projects rules of measurement against performance which would include Earned Value Management and the Reporting Structure?

True

False

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Defining specific tasks and outlining resources, facilitating Communication and integrating project specific plans to include the triple constraint is part of which critical process?

Project Charter

Project (SOW)

Configuration Management

WBS

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?