PMBoK - STAKEHOLDER

PMBoK - STAKEHOLDER

1st - 12th Grade

7 Qs

quiz-placeholder

Similar activities

Project Controls PC 06 Rev 02

Project Controls PC 06 Rev 02

1st Grade

12 Qs

TKO Stakeholder Quiz

TKO Stakeholder Quiz

1st Grade - Professional Development

10 Qs

PM Quiz - Stakeholder Management

PM Quiz - Stakeholder Management

1st - 3rd Grade

10 Qs

Basic Elements of a Personal Computer System

Basic Elements of a Personal Computer System

8th Grade

10 Qs

PMI SH - Plan and Manage Schedule

PMI SH - Plan and Manage Schedule

1st - 3rd Grade

8 Qs

Latsar

Latsar

4th Grade

10 Qs

Basic Project Management Training

Basic Project Management Training

1st - 3rd Grade

10 Qs

Sharing Session - Warehouse Project Management

Sharing Session - Warehouse Project Management

1st - 3rd Grade

10 Qs

PMBoK - STAKEHOLDER

PMBoK - STAKEHOLDER

Assessment

Quiz

Professional Development

1st - 12th Grade

Hard

Created by

Andi Nirmala

Used 8+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. Which of the following process is in monitoring and controlling process group?

Plan stakeholder engagement

Identify stakeholder

Manage stakeholder engagement

Monitor stakeholder engagement

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which strategy when the stakeholders are in High Power but Low Interset?

Keep Informed

Manage Closely

Monitor

Keep Satisfied

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which Engagement Level where the Stakeholder actively engage for project success?

Leading

Supportive

Unaware

Neutral

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is one important output when Managing Stakeholder Engagement?

Interpersonal skill

Issue log

Stakeholder register

Stakeholder management plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an output of Monitor Stakeholder Engagement?

Information management system

Issue log

Change request

Stakeholder register

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of the following that is not included in Saliance Model?

Power

Interest

Legitimacy

Urgency

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT an output of Identify Stakeholder process?

Stakeholder register

Stakeholder engagement register

Change request

Project document updates