PROJMA Ch.6 Developing a Project Schedule

Authored by Shieldon Yparraguirre

Business

1st - 3rd Grade

Used 2+ times

PROJMA Ch.6 Developing a Project Schedule
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is a tool used for planning, scheduling, and monitoring project progress?

Process Network

Project Network

Planning Network

Progress Network

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Activity is an element in the project that consumes time (for example, work, waiting) and can include one or more work packages.

TRUE

FALSE

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

These are the primary inputs for developing a project network plan

Task Packages

Work Packages

Work Plan

Task Plan

4.

FILL IN THE BLANKS QUESTION

30 sec • 1 pt

(a)   are activities that can take place at the same time

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The earliest an activity can start or finish based on network logic, the data date and any schedule constraint

Late Time

Early Time

Mid Time

Dawn Time

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The latest an activity can start or finish without delaying the completion of the project

Late Time

Latest Time

Early Time

Earliest Time

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Burst Activity is an activity that has less than 1 activity following it

TRUE

FALSE

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?