1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Whats is Construction Management?

It is a professional service that uses specialised, project management techniques to oversee the planning, design and construction of a project, from its beginning to ite end

It is the process of putting a project plan into action to produce the deliverables, otherwise known as the products or services, for clients or stakeholders.

It uses processes, skills, tools and knowledge to complete a planned project and achieve its goals. It differs from general management because of the limited scope of a project, concrete deadlines and specific deliverables.

None of the above

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the triple constraints of Project Management?

site, cost and quality

brief, cost and time

time, cost and quality

time, quality and scope

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Construction Manager is based at the headquarters and job site. True or False?

True

False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who deals with construction workers, equipment and materials?

Project Manager

Project Implementor

Construction Manager

All of the above

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What insurances are required during the construction stage of a building porejct?

Fire, Banker's Guarantee, Workman Compensation

Fire, Public Liability & Worker's Coverage

Fire, Public Liability & Workman Compensation

Fire, Public-Private Liability & Worker's Coverage

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

RIBA specimen checklists and forms can be obtained from... ?

RIBA Plan of Work 2020

RIBA Handbook of Practice Management

RIBA Plan of Work 2013

RIBA Job Book & RIBA website

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the event of an omission or a substitution during construction stage requiring revisions to detail design, alert the client to any ...

additional costs

additional fees

alterations to the Project Programme

All of the above

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Education