B339_L07_Quiz to Recap L05 to L07

B339_L07_Quiz to Recap L05 to L07

11th Grade

11 Qs

quiz-placeholder

Similar activities

Telecommunication Sytem

Telecommunication Sytem

7th Grade - University

10 Qs

Anatomy 6.1 - Overview of Nervous system

Anatomy 6.1 - Overview of Nervous system

11th - 12th Grade

16 Qs

INFORMATIKA 11 S2 HAL 026 PA 1

INFORMATIKA 11 S2 HAL 026 PA 1

11th Grade

10 Qs

RO81 LO1 Mood boards

RO81 LO1 Mood boards

9th - 11th Grade

10 Qs

untitled

untitled

11th Grade

10 Qs

Plant Parts and Functions

Plant Parts and Functions

9th - 12th Grade

10 Qs

OCR GCSE Computer Science Variety Quiz 3

OCR GCSE Computer Science Variety Quiz 3

9th - 11th Grade

12 Qs

EKG Vocab

EKG Vocab

11th Grade

10 Qs

B339_L07_Quiz to Recap L05 to L07

B339_L07_Quiz to Recap L05 to L07

Assessment

Quiz

Other, Specialty, Professional Development

11th Grade

Medium

Created by

Ji Ong

Used 1+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following documents covers the deliverables in a project?

Work Breakdown Structure

Close Out Document

Risk Identification Matrix

Stake Holder Listing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Aaron, the project manager is using the 3-point estimation to calculate the estimated duration of a project. The optimistic, most likely and pessimistic durations are respectively: 4, 6 and 9 days. Which is the correct formulae Aaron should use for his calculation?

(4 + 6 + 9)/3

(4*4 + 6 + 9)/6

(4 + 6*4 + 9)/6

(4*2 + 6*2 + 9)/6

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

   Which of the following will NOT affect the estimation of a project’s cost resulting in negative consequences?

The political situation

A scope statement that is not specific

A Bottom-up approach to cost estimation

Additional deliverables that the client really wants

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Work Breakdown Structure (WBS) is an important tool used during the Planning phase of project management. Which of the following statements correctly identifies what is broken down in a WBS?

The team member’s leave plans during the duration of the project

Project costs are broken down into the various departments that they need to be charged against

Project tasks are broken down into tasks and activities

Major risks that need to be mitigated in order for the project to be completed on time

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does RACI stand for ____________ ?

Reasonable, Accountable, Considered, Informal

Responsible, Accountable, Consulted, Informed

Reasonable, Accountable, Communicative, Informed

Responsible, Accurate, Consulted, Informative

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Zootopia Café is implementing a cashless payment system. Hamid, the HR Manager, has been copied on all the meeting minutes by the project team. What role does Hamid play in a RACI Matrix?

Responsible

Accountable

Consulted

Informed

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How are dependencies between tasks denoted in a network node diagram?  

A box

An arrow

By a dot

A diamond-shaped box

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?