DE Course Project Documentation and Close-Out

DE Course Project Documentation and Close-Out

Assessment

Quiz

Created by

CSSD BOC

Professional Development

KG

3 plays

Hard

Student preview

quiz-placeholder

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Contractor must present proof of submission of its DPWH-approved CSHP, albeit pending concurrence by DOLE, in order for its claim for advance payment or first billing to be processed.

TRUE

FALSE

2.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Upon issuance by the DPWH of the NTP, the IO shall provide the contractor with an editable file of the approved original plan of the project in order to facilitate the as-staked plan.

TRUE

FALSE

3.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

If the contractor fails to submit the as-staked plan on time for processing, the contractor shall submit to the IO a request for one (1) time extension of at least fifteen (15) days depending on the project cost.

TRUE

FALSE

4.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Upon issuance of Notice to Proceed, the approve CSHP is among the list of required documents to be submitted.

TRUE

FALSE

5.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

When the contractor incurred a negative 10% slippage, the contractor shall be issued a final warning and required to come-up with a more detailed program of activities with weekly physical targets, together with the required additional input resources.

TRUE

FALSE

6.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

When the contractor incurred a negative 15% slippage, the Implementing Office shall prepare contingency plans for the termination of the contract and/or take-over of the work by administration or contract.

TRUE

FALSE

7.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

In case the total sum of liquidated damages reaches ten percent (10%) of the total contract price, the Procuring Entity may allow the contractor to continue the works without prejudice to the continued imposition of liquidated damages until the works have been completed.

TRUE

FALSE

8.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

The D.O. 99, Series of 2016 prescribes the guidelines on the issuance of Certificate of Completion and Certificate of Acceptance

TRUE

FALSE

9.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

The contractor shall take all reasonable precautions to maintain the health and safety of his personnel based on the Construction Safety and Health Program (CSHP) duly concurred by the DPWH.

TRUE

FASE

10.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

The CoA shall be issued by the Head of IO after the one-year DLP after all defects/deficiencies, if any, shall have been repaired by the Contractor to the satisfaction of the same Inspectorate Team and upon extension of the Performance Security up to one year by the Contractor.

TRUE

FALSE

Explore all questions with a free account

or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?