1.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Contractor must present proof of submission of its DPWH-approved CSHP, albeit pending concurrence by DOLE, in order for its claim for advance payment or first billing to be processed.

TRUE

FALSE

2.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Upon issuance by the DPWH of the NTP, the IO shall provide the contractor with an editable file of the approved original plan of the project in order to facilitate the as-staked plan.

TRUE

FALSE

3.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

If the contractor fails to submit the as-staked plan on time for processing, the contractor shall submit to the IO a request for one (1) time extension of at least fifteen (15) days depending on the project cost.

TRUE

FALSE

4.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

Upon issuance of Notice to Proceed, the approve CSHP is among the list of required documents to be submitted.

TRUE

FALSE

5.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

When the contractor incurred a negative 10% slippage, the contractor shall be issued a final warning and required to come-up with a more detailed program of activities with weekly physical targets, together with the required additional input resources.

TRUE

FALSE

6.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

When the contractor incurred a negative 15% slippage, the Implementing Office shall prepare contingency plans for the termination of the contract and/or take-over of the work by administration or contract.

TRUE

FALSE

7.

MULTIPLE CHOICE QUESTION

30 sec • 5 pts

In case the total sum of liquidated damages reaches ten percent (10%) of the total contract price, the Procuring Entity may allow the contractor to continue the works without prejudice to the continued imposition of liquidated damages until the works have been completed.

TRUE

FALSE

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?