1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
1. Project purpose, project approval requirements, stakeholder's influences, summary budget, milestone schedule should include in the ………… In the project integration management process.
A. Close the project or phase
B. Execute project plan
C. project management plan
D. Project charter
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
2. Stakeholders in a project can be defined as:
A. The project managers and workers.
B. Management, Funding body, sponsor, customer both internal and external, and suppliers
C. Internal and external customers
D. The sponsors and project managers.
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3. Gantt charts display project tasks, task groups, deadlines, task duration, assignments, and other such information in what format?
A. In a pie graph.
B. In a detailed task report.
C. Along a horizontal timeline.
D. All of the above.
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4. _____________ is an important element in the project planning cycle.
A. Project objective
B. Project idea
C. Project identification
D. Project selection
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5. Relevant project specifications are often affected by all except the following:
A. The support of project officers
B. Legislation, regulations, standards and codes of practice
C. Manufacturer’s specifications, schedules, manuals and catalogues
D. Policy and/or guidelines, government and/or industry
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6. Planning and controlling the task is the ________________of a project manager.
A. strategy
B. responsibility
C. procedure
D. duty
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7. Resources required for a project include
A. People, buildings, equipment and purchases
B. Expenses, security and cleaners
C. Managers, equipment and expenses
D. Budget, building and expenses
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?