Chapt4

Chapt4

1st Grade

10 Qs

quiz-placeholder

Similar activities

001. Pre & Post Test PMP Des 2024

001. Pre & Post Test PMP Des 2024

1st Grade

12 Qs

06. Schedule Management

06. Schedule Management

1st - 3rd Grade

12 Qs

PMI-SH Plan and Manage Quality of Products/deliverables

PMI-SH Plan and Manage Quality of Products/deliverables

1st Grade

13 Qs

Communication Management

Communication Management

1st - 3rd Grade

10 Qs

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

PMI-SH Manage Project/phase Closure or Transitions

PMI-SH Manage Project/phase Closure or Transitions

1st Grade

15 Qs

training 8 aug ciast - muhaimin

training 8 aug ciast - muhaimin

1st - 5th Grade

10 Qs

PMI SH - Plan and Manage Project Compliance

PMI SH - Plan and Manage Project Compliance

1st - 3rd Grade

14 Qs

Chapt4

Chapt4

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

WS Ho

Used 6+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

A work breakdown structure numbering system allows the project team to:

A. Systematically estimate costs of work breakdown structure elements

B. Provide project justification

C. Identify the level at which individual elements are found

D. Use it in project management software

2.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following is a KEY output of the Validate Scope process?

A. A more complete scope management plan

B. Customer acceptance of project deliverables

C. Improved schedule estimates

D. An improved project management information system

3.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of work packages?

A. WBS dictionary

B. Activity list

C. Project scope statement

D. Scope management plan

4.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to

A. Let the sponsor know of the stakeholders' request

B. Evaluate the impact of adding the scope

C. Tell the stakeholders the scope cannot be added

D. Add the work if there is time available in the project schedule

5.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

You have just joined the project management office after five years of working on projects. One of the things you want to introduce to your company is the value of creating and utilizing work breakdown structures. Some of the project managers are angry that you are asking them to do "extra work." Which of the following would be the BEST thing you could tell the project managers to convince them to use work breakdown structures?

A. Work breakdown structures will prevent work from slipping through the cracks

B. Work breakdown structures are only needed on large projects

C. Work breakdown structures are required only if the project involves contracts

D. Work breakdown structures are the only way to identify risks.

6.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

During a project team meeting, a team member suggests an enhancement to the scope that is beyond the scope of the project charter. The project manager points out that the team needs to concentrate on completing all the work and only the work required. This is an example of:

A. Change management process

B. Scope management

C. Quality analysis

D. Scope decomposition

7.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

A project manager may use to make sure the team members clearly know what work is included in each of their work packages.

A. The project scope statement

B. The product scope

C. The WBS dictionary

D. The schedule

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?