Which is NOT a rationale for reducing project duration ?

Time to market

Unforeseen delays

Gut feeling

Incentive contracts

2.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

Which are Unforeseen delays which might be a reason to reduce project duration?

Adverse weather

Design Flaws

Gut feeling

Equipment Breakdown

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

The following are options for reducing project duration when Resources Are Not Constrained, except for:

Adding Resources

Outsourcing Project Work

Hold and stop

Scheduling Overtime

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

True or False: Compromising quality is an option When Resources Are Constrained?

True

False

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

True or False: Crashing activities increases indirect costs.

True

False

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is the term used to shorten an activity?

Crash Cost

Crashing

Crash Time

Crash Point

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

What is the shortest possible time an activity can realistically be completed?

Crash Cost

Crashing

Crash Time

Crash Point

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?