1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

This is the shortest possible time in which the activity can be finished. It assumes that everything goes well.

Optimistic

Pessimistic

Most Likely

Accurate

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  • The longest possible time required to perform an activity under extremely bad conditions

Optimistic

Pessimistic

Most Likely

Accurate

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Critical path is the

shortest time path in a network 

longest time path in a network 

efficient time path in a network 

optimal time path in a network 

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Activities with zero slack lie on a

Non-Critical path

Critical path

Normal path

Crash path

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ______ is a graphical representation of arrows and nodes for showing logical sequence of activities performed to achieve a project objectives.

Bar

Network

Chart

Diagram

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If duration of each activity in a project scheduling is not known with certainty then ____ network model is used

CPM

PERT

PEST

Deterministic

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

________ analysis is used for planning, scheduling and controlling large complex projects.

Transportation

LPP

Network

Assignment

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?