1.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:

abstract dependency

discretionary dependency

external dependency

mandatory dependency

2.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

The project manager and team have created the schedule for the hospital wireless network upgrade project. The schedule includes a five-day delay for the network approval before the hospital can use the upgraded network. This causes the finish date of the project to slip by five days. This hospital network project is:

accelerating

forming

lagging

leading

3.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Which process puts more resources on the critical path?

crashing

fast tracking

leading

shortening

4.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Which process puts more resources on the critical path?

1. Activity e with preceding activities STart, and duration of 8 days

2. Activity F with preceding activities E and duration of 4 days

3. Activity G with preceding activities E and duration of 10 days

4. Activity H with preceding activities F and G and duration of 2 days

5. Activity I with preceding activities H and duration of 2 days

6. Activity J with preceding activities H and duration of 2 days

7. Activity K with preceding activities H and duration of 3 daus

8. Activity L with preceding activities I, J, and K and duration of 2 days

9. Activity M with preceding activities L and duration of 1 day

19 days

25 days

26 days

27 days

5.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

Which process requires the project manager to analyze the network diagram and sequencing to see whether any activities can be done in parallel on the critical path?

crashing

fast tracking

leading

shortening

6.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

In order to complete the finished attic remodel project on time, Brian decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:

crashing

fast tracking

leading

shortening

7.

MULTIPLE CHOICE QUESTION

30 sec โ€ข 1 pt

It took Scott's team two hours to mow and edge one acre of land. He estimates that it will take his team eight hours to mow and edge four acres of land for an upcoming project. Scott's duration estimation for this project is an example of:

bottom up estimating

parametric estimating

reserve analysis

three point estimating

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?