What is a recommended method for controlling change within a project?
Project Integration Management Quiz

Quiz
•
Professional Development
•
Professional Development
•
Medium
Michael Myers
Used 5+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Have only the project manager able to initiate change.
Have each change approved or rejected through a formal change control process
Allow each project member ultimate control of changes within their part of the project without a review process
Freeze scope and allow absolutely no changes
Answer explanation
The change control procedure varies from project to project. However, every change request must be processed through a formal change control process.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager calls you in as a consultant to provide input on developing the Project Charter. According to the PMBOK, your contribution to the project could best be termed as:
Professional Consultant
Expert Judgment
Charter Consultant
Expert Consultancy
Answer explanation
Expert Judgment is judgment provided, based on expertise in an application area, a knowledge area, a discipline, an industry, etc. Expert Judgment is available from many sources including consultants.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which process is concerned with providing forecasts to update current cost information?
Monitor and Control Project Work
Project Management Information System
Close Project or Phase
Direct and Manage Project Work
Answer explanation
During the Monitor and Control Project Work process, work performance data is gathered and passed to the controlling processes. The Monitor and Control Project Work process is responsible for keeping track of the all project's measures, including cost.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following would not be considered an Enterprise Environmental Factor during the Develop Project Charter process?
Scope Statement
Organizational infrastructure
Governmental standards
Marketplace conditions
Answer explanation
The scope statement is clearly not an enterprise environmental factor, whereas the other three choices—governmental standards, organizational infrastructure, and marketplace conditions—are enterprise environmental factors.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The Close Project or Phase process is not performed when:
Cancelling projects
Closing projects
Closing project phases
Reactivating projects
Answer explanation
The Close Project or Phase process allows the project manager to close or finish a specific phase of the project.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of these tools and techniques is common to all seven Project Integration Management processes?
Meetings
Data analysis
Data gathering
Expert Judgment
Answer explanation
All seven processes of Project Integration Management use Expert Judgment as a tool and technique.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are beginning a new project. When should you use the Perform Integrated Change Control process?
Throughout the entire project
Only when closing out the project
Only after the project is completely funded
Only after the project scope is clearly defined
Answer explanation
Changes can occur in the project at any time. The Perform Integrated Change Control process is valuable for managing and tracking those changes.
Create a free account and access millions of resources
Similar Resources on Quizizz
8 questions
Planning for Success Part 1

Quiz
•
Professional Development
10 questions
Project Scope Management

Quiz
•
Professional Development
6 questions
Validate and Control Scope - Assignment

Quiz
•
Professional Development
10 questions
Project Management Master Class 3

Quiz
•
Professional Development
15 questions
Proj Integration Management

Quiz
•
Professional Development
12 questions
Project management principles

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 2

Quiz
•
Professional Development
15 questions
Kuis 1 Project Administration

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade