Search Header Logo

Project Management Part 2

Authored by Ip faleh

Professional Development

1st Grade

Used 1+ times

Project Management Part 2
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The PERT estimation technique:

uses the pessimistic, optimistic and most likely estimates to make the estimates
uses the pessimistic, optimistic and most likely estimates to make the estimates, with a bias towards the pessimistic estimates, to have more flexibility in the schedule
uses the pessimistic, optimistic and most likely estimates to make the estimates, with a bias towards the most likely estimates, to arrive at a weighted average
uses the pessimistic, optimistic and most probable estimates to make the estimates with a bias towards the optimistic estimates, to provide a stimulating challenge to the project team

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The correct rule to follow by organizations that have not defined the margin of precision for estimating the order of magnitude is:

-25% to +75%
0% to +100%
-15% to +50%
-5% to +10%.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Contingencies (contingency reserves) are

funds paid into a personal account to ensure regulatory compliance
used for bonuses at the end of a successful project
a representation of the level of confidence in the project estimates
always included in each particular estimate

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A network diagram should represent

a breakdown of the total amount of work required for the project
linkages between project activities
the network required to support the technical infrastructure
the relationship of the critical path to the non-critical paths.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A path in a network diagram is represented by:

a series of related tasks
all tasks that have one or more predecessors
all tasks that have one or more successors
1 and 3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To ensure that a project stays on schedule, a project manager must:

manage according to the critical path
send a progress report to all stakeholders
reduce activity estimates to meet deadlines
manage the stakeholder expectations.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In managing the duration of an activity, the best technique is to manage according to:

from the start date at the latest
the date set for completing the activity
the less solid path
percentage complete

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?