Project Management Part 2

Project Management Part 2

1st Grade

30 Qs

quiz-placeholder

Similar activities

CAPM-Domain#2 - Predictive, Plan-based Methodologies

CAPM-Domain#2 - Predictive, Plan-based Methodologies

1st Grade

27 Qs

SC202- Content & Pedagogical Approaches in Science for ECE-

SC202- Content & Pedagogical Approaches in Science for ECE-

KG - University

25 Qs

Quiz8

Quiz8

1st Grade

26 Qs

Pre-Test RPA Learning Guide Self Learning

Pre-Test RPA Learning Guide Self Learning

1st - 4th Grade

25 Qs

UE 3Lessons Combined

UE 3Lessons Combined

1st Grade

30 Qs

POST TES

POST TES

1st Grade - University

26 Qs

30/365 Quiz

30/365 Quiz

1st Grade

30 Qs

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

1st - 3rd Grade

28 Qs

Project Management Part 2

Project Management Part 2

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

Ip faleh

Used 1+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The PERT estimation technique:
uses the pessimistic, optimistic and most likely estimates to make the estimates
uses the pessimistic, optimistic and most likely estimates to make the estimates, with a bias towards the pessimistic estimates, to have more flexibility in the schedule
uses the pessimistic, optimistic and most likely estimates to make the estimates, with a bias towards the most likely estimates, to arrive at a weighted average
uses the pessimistic, optimistic and most probable estimates to make the estimates with a bias towards the optimistic estimates, to provide a stimulating challenge to the project team

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The correct rule to follow by organizations that have not defined the margin of precision for estimating the order of magnitude is:
-25% to +75%
0% to +100%
-15% to +50%
-5% to +10%.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Contingencies (contingency reserves) are
funds paid into a personal account to ensure regulatory compliance
used for bonuses at the end of a successful project
a representation of the level of confidence in the project estimates
always included in each particular estimate

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A network diagram should represent
a breakdown of the total amount of work required for the project
linkages between project activities
the network required to support the technical infrastructure
the relationship of the critical path to the non-critical paths.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A path in a network diagram is represented by:
a series of related tasks
all tasks that have one or more predecessors
all tasks that have one or more successors
1 and 3

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

To ensure that a project stays on schedule, a project manager must:
manage according to the critical path
send a progress report to all stakeholders
reduce activity estimates to meet deadlines
manage the stakeholder expectations.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In managing the duration of an activity, the best technique is to manage according to:
from the start date at the latest
the date set for completing the activity
the less solid path
percentage complete

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?