
Project Management Part 2
Authored by Ip faleh
Professional Development
1st Grade
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The PERT estimation technique:
uses the pessimistic, optimistic and most likely estimates to make the estimates
uses the pessimistic, optimistic and most likely estimates to make the estimates, with a bias towards the pessimistic estimates, to have more flexibility in the schedule
uses the pessimistic, optimistic and most likely estimates to make the estimates, with a bias towards the most likely estimates, to arrive at a weighted average
uses the pessimistic, optimistic and most probable estimates to make the estimates with a bias towards the optimistic estimates, to provide a stimulating challenge to the project team
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The correct rule to follow by organizations that have not defined the margin of precision for estimating the order of magnitude is:
-25% to +75%
0% to +100%
-15% to +50%
-5% to +10%.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Contingencies (contingency reserves) are
funds paid into a personal account to ensure regulatory compliance
used for bonuses at the end of a successful project
a representation of the level of confidence in the project estimates
always included in each particular estimate
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A network diagram should represent
a breakdown of the total amount of work required for the project
linkages between project activities
the network required to support the technical infrastructure
the relationship of the critical path to the non-critical paths.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A path in a network diagram is represented by:
a series of related tasks
all tasks that have one or more predecessors
all tasks that have one or more successors
1 and 3
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
To ensure that a project stays on schedule, a project manager must:
manage according to the critical path
send a progress report to all stakeholders
reduce activity estimates to meet deadlines
manage the stakeholder expectations.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In managing the duration of an activity, the best technique is to manage according to:
from the start date at the latest
the date set for completing the activity
the less solid path
percentage complete
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?