A good project manager always gathers and documents lessons learned throughout the project lifecycle rather than delaying the effort until the project closure. Which of the following is not a risk associated with postponing the lessons-learned gathering effort until the very end of the project?
Practice Exam 2 Part 1

Quiz
•
Professional Development
•
Professional Development
•
Hard
Michael Myers
Used 4+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project manager has fewer resources available.
The project's earned value decreases
Not all lessons learned might get captured
The effort might seem boring and non-value-adding
Answer explanation
The risk of delaying the lessons learned gathering exercise till the very end of the project is that the gathered information might not be completed because the project manager will not have the whole team available rather than those working on the closing phase. Further, this exercise might seem boring and bureaucratic.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Laurence is the PMO manager at ANZ Company. The CEO of the company asked Laurence to review the business requirements and develop the current year’s capital management plan. The capital management plan will outline the key business deliverables (capital projects) and will go to the board for final approval. Which of the following organizational artifacts should Laurence review to analyze the business requirements for the current fiscal year?
Lessons Learned
Capital Budget for the current year
Organizational Process Assets
Organizational Strategy
Answer explanation
Capital planning is the process of budgeting resources for the future of an organization's long term plans. Capital planning for a business would include budgeting for new and replacement machinery, research and development and the production of new products, new plants and other major capital projects. Capital projects can only achieve the organizational goals when they are aligned with the organization’s strategy.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Maintaining good supplier relationships should be important to all project managers. A good buyer-seller relationship is a partnership that results in a win-win situation that nurtures both parties. Which of the following is both a short- and long-term benefit of treating a supplier with courtesy, honesty, and fairness?
There is no need to have formal contracts in place
Delivery of quality products and services at the best price
The buyer can delay the payments without jeopardizing the relationship
The supplier can charge a price higher than the market price
Answer explanation
Charging higher than market price or delaying the payment will damage the relationship in the long-run. Further formal contracts should always be in place as it is a good project management practice and it mitigates risk for both parties and avoids conflicts. The benefit of a good supplier relationship is delivery of quality products at competitive prices.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
James is managing a shopping mall construction project. During the project execution, he learns the project communications management plan is not effective and requires a major update. Which of the following processes will issue a change request for the required update?
Plan Communications Management
Manage Communications
Perform Integrated Change Control
Monitor Communications
Answer explanation
Change request is an output of the Monitor Communications process. The Monitor Communications process will produce the change request, the Perform Integrated Change Control process will get that approved, and then the Plan Communications Management process will make the necessary updates.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
With a growing awareness of so-called unknowable-unknowns, the existence of emergent risk is becoming clear. These are risks that can only be recognized after they have occurred. Emergent risks can be tackled through developing:
Project resilience
Project charter
Project management plan
Project risk management plan
Answer explanation
Emergent risks can be tackled through developing project resilience. This requires each project to have right level of budget and schedule contingencies, flexible project processes, empowered project team and frequent review of early warning signs.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Change control tool selection should be based on the needs of the project stakeholders, including organizational and environmental considerations and/or constraints. Which of the following is not a key change management consideration while selecting an appropriate change control tool for a project?
Identifying and selecting a change item
Configuration item verification and audit
Documenting the change into a proper change request
Tracking change requests
Answer explanation
Configuration item verification and audit is related to configuration management instead of change management.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In general, Perform Qualitative Risk Analysis is:
Not often completed
Complete and 100 percent accurate
In-depth and thorough
focused on high-priority risks
Answer explanation
Perform Qualitative Risk Analysis is quicker than Perform Quantitative Risk Analysis as it focuses on high-priority risks.
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
Introduction to Project Management

Quiz
•
Professional Development
10 questions
PROJECT RISK MANAGEMENT

Quiz
•
Professional Development
15 questions
Introduction to Project Management for MT Nestle

Quiz
•
Professional Development
10 questions
Project Management Fundamentals - Module 5

Quiz
•
Professional Development
11 questions
Basics of Project management

Quiz
•
Professional Development
10 questions
Project Management Master Class 3

Quiz
•
Professional Development
10 questions
Project Closure

Quiz
•
Professional Development
9 questions
Planning and Scheduling Professional Practice Questions

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade