Practice Exam 2 Part 1

Practice Exam 2 Part 1

Professional Development

11 Qs

quiz-placeholder

Similar activities

Review on Project Management Concepts

Review on Project Management Concepts

Professional Development

10 Qs

Project Integration Management

Project Integration Management

Professional Development

15 Qs

Project Management

Project Management

Professional Development

15 Qs

Quizziz 3- Knowledge Area 3 and 5

Quizziz 3- Knowledge Area 3 and 5

Professional Development

10 Qs

Duration Estimate In Work Program

Duration Estimate In Work Program

Professional Development

10 Qs

Project Execution & Monitoring

Project Execution & Monitoring

Professional Development

12 Qs

Practice Exam 2 Part 2

Practice Exam 2 Part 2

Professional Development

10 Qs

SG20_Test_S5_CH6 Schedule

SG20_Test_S5_CH6 Schedule

Professional Development

10 Qs

Practice Exam 2 Part 1

Practice Exam 2 Part 1

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Michael Myers

Used 4+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A good project manager always gathers and documents lessons learned throughout the project lifecycle rather than delaying the effort until the project closure. Which of the following is not a risk associated with postponing the lessons-learned gathering effort until the very end of the project?

The project manager has fewer resources available.

The project's earned value decreases

Not all lessons learned might get captured

The effort might seem boring and non-value-adding

Answer explanation

The risk of delaying the lessons learned gathering exercise till the very end of the project is that the gathered information might not be completed because the project manager will not have the whole team available rather than those working on the closing phase. Further, this exercise might seem boring and bureaucratic.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Laurence is the PMO manager at ANZ Company. The CEO of the company asked Laurence to review the business requirements and develop the current year’s capital management plan. The capital management plan will outline the key business deliverables (capital projects) and will go to the board for final approval. Which of the following organizational artifacts should Laurence review to analyze the business requirements for the current fiscal year?

Lessons Learned

Capital Budget for the current year

Organizational Process Assets

Organizational Strategy

Answer explanation

Capital planning is the process of budgeting resources for the future of an organization's long term plans. Capital planning for a business would include budgeting for new and replacement machinery, research and development and the production of new products, new plants and other major capital projects. Capital projects can only achieve the organizational goals when they are aligned with the organization’s strategy.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Maintaining good supplier relationships should be important to all project managers. A good buyer-seller relationship is a partnership that results in a win-win situation that nurtures both parties. Which of the following is both a short- and long-term benefit of treating a supplier with courtesy, honesty, and fairness?

There is no need to have formal contracts in place

Delivery of quality products and services at the best price

The buyer can delay the payments without jeopardizing the relationship

The supplier can charge a price higher than the market price

Answer explanation

Charging higher than market price or delaying the payment will damage the relationship in the long-run. Further formal contracts should always be in place as it is a good project management practice and it mitigates risk for both parties and avoids conflicts. The benefit of a good supplier relationship is delivery of quality products at competitive prices.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

James is managing a shopping mall construction project. During the project execution, he learns the project communications management plan is not effective and requires a major update. Which of the following processes will issue a change request for the required update?

Plan Communications Management

Manage Communications

Perform Integrated Change Control

Monitor Communications

Answer explanation

Change request is an output of the Monitor Communications process. The Monitor Communications process will produce the change request, the Perform Integrated Change Control process will get that approved, and then the Plan Communications Management process will make the necessary updates.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

With a growing awareness of so-called unknowable-unknowns, the existence of emergent risk is becoming clear. These are risks that can only be recognized after they have occurred. Emergent risks can be tackled through developing:

Project resilience

Project charter

Project management plan

Project risk management plan

Answer explanation

Emergent risks can be tackled through developing project resilience. This requires each project to have right level of budget and schedule contingencies, flexible project processes, empowered project team and frequent review of early warning signs.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Change control tool selection should be based on the needs of the project stakeholders, including organizational and environmental considerations and/or constraints. Which of the following is not a key change management consideration while selecting an appropriate change control tool for a project?

Identifying and selecting a change item

Configuration item verification and audit

Documenting the change into a proper change request

Tracking change requests

Answer explanation

Configuration item verification and audit is related to configuration management instead of change management.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In general, Perform Qualitative Risk Analysis is:

Not often completed

Complete and 100 percent accurate

In-depth and thorough

focused on high-priority risks

Answer explanation

Perform Qualitative Risk Analysis is quicker than Perform Quantitative Risk Analysis as it focuses on high-priority risks.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?