Practice Exam 2 Part 3

Practice Exam 2 Part 3

Professional Development

10 Qs

quiz-placeholder

Similar activities

Waterfall Mindset1(AKF)

Waterfall Mindset1(AKF)

Professional Development

12 Qs

Project Scope Management

Project Scope Management

Professional Development

10 Qs

Quiz Lesson 6 - Topic A (Project/Phase Closure)

Quiz Lesson 6 - Topic A (Project/Phase Closure)

Professional Development

8 Qs

CAPM 1 (10 Questions)

CAPM 1 (10 Questions)

Professional Development

10 Qs

Project Priority Matrix

Project Priority Matrix

Professional Development

13 Qs

Project Management Master Class 2

Project Management Master Class 2

Professional Development

12 Qs

Project Management Master Class 3

Project Management Master Class 3

Professional Development

10 Qs

Construction Cost Estimating and Analysis Special Quiz

Construction Cost Estimating and Analysis Special Quiz

Professional Development

5 Qs

Practice Exam 2 Part 3

Practice Exam 2 Part 3

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Michael Myers

Used 2+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of these is not an established Estimate Activity Durations technique?

Three Point Estimating

Parametric Estimating

Analogous Estimating

Critical Path Estimation

Answer explanation

Analogous, parametric, and three-point estimating techniques are all accepted practices for determining the correct amount of time required for a portion of the project. The Critical Path Analysis techniques evaluate the whole project schedule.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

If you are working on a project where there is no definite detailed scope, but there are similar projects in the past, what is the correct Estimate Activity Durations tool to use?

Analogous Estimating

Parametric Estimating

Critical Path Estimation

Three Point Estimating

Answer explanation

Analogous estimation relies on comparing a project to previous projects that were similar in nature.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

As project manager, you would like to show the relationship between two variables to help your project team understand the quality impact better. Which tool should you use?

Scatter Diagram

Run Chart

Fishbone Diagram

Pareto Chart

Answer explanation

A scatter diagram plots several occurrences of two variables (one on each axis). Often a relationship between the two variables can then be determined, based on how closely they fit a geometric model.

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project manager feels the need of updating one of the project supplier contracts to meet the project’s current needs. However, before any change requests, the project manager must know the right process to incorporate a change into this specific contract. What should he do first?

Issue the change request and get it approved through Integrated Change Control process

Update the project procurements management plan

Review the change request handling procedure as documented in the contract itself

Review alternative dispute resolution (ADR) procedures in the contract

Answer explanation

The first step should be to gather enough information so that the right decision and course of action can be determined. The second step should be to issue a change request and follow its approval. The project manager must first review the change request handling procedure specific to the contract and that can be found in the procurement contract itself.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The objective of a transformation project is to move an organization from one state to another state. The desired result of the change driven by the project is described as the:

Good state

Future state

Happy state

Transition state

Answer explanation

Before the project begins, the organization is commonly referred to as being in the current state. The desired result of the change derived by the project is described as the future state.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The term Progressive Elaboration incorrectly represents which of the following?

Changes to project scope

Rolling wave planning

Detailing out the product requirements developed during the initiation process.

Production of fabrication and construction drawings from the design drawings for a chemical plant.

Answer explanation

The distinction between progressive elaboration and scope creep needs to be understood since the two terms are different. The changes to scope (especially in an uncontrolled manner) are called scope creep. In contrast, progressive elaboration involves building on or elaborating the output of a previous phase.

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which document describes the project's deliverables and the work required to create those deliverables?

Project authorization document

Project scope statement

Project scope management plan

Project charter

Answer explanation

The project scope statement is the correct response. This document describes the project's deliverables in detail and the work that is required to create those deliverables. It also forms the baseline for evaluating whether requests for changes are within or outside the project's boundaries.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?