Which of these is not an established Estimate Activity Durations technique?
Practice Exam 2 Part 3

Quiz
•
Professional Development
•
Professional Development
•
Hard
Michael Myers
Used 2+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Three Point Estimating
Parametric Estimating
Analogous Estimating
Critical Path Estimation
Answer explanation
Analogous, parametric, and three-point estimating techniques are all accepted practices for determining the correct amount of time required for a portion of the project. The Critical Path Analysis techniques evaluate the whole project schedule.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
If you are working on a project where there is no definite detailed scope, but there are similar projects in the past, what is the correct Estimate Activity Durations tool to use?
Analogous Estimating
Parametric Estimating
Critical Path Estimation
Three Point Estimating
Answer explanation
Analogous estimation relies on comparing a project to previous projects that were similar in nature.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
As project manager, you would like to show the relationship between two variables to help your project team understand the quality impact better. Which tool should you use?
Scatter Diagram
Run Chart
Fishbone Diagram
Pareto Chart
Answer explanation
A scatter diagram plots several occurrences of two variables (one on each axis). Often a relationship between the two variables can then be determined, based on how closely they fit a geometric model.
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A project manager feels the need of updating one of the project supplier contracts to meet the project’s current needs. However, before any change requests, the project manager must know the right process to incorporate a change into this specific contract. What should he do first?
Issue the change request and get it approved through Integrated Change Control process
Update the project procurements management plan
Review the change request handling procedure as documented in the contract itself
Review alternative dispute resolution (ADR) procedures in the contract
Answer explanation
The first step should be to gather enough information so that the right decision and course of action can be determined. The second step should be to issue a change request and follow its approval. The project manager must first review the change request handling procedure specific to the contract and that can be found in the procurement contract itself.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The objective of a transformation project is to move an organization from one state to another state. The desired result of the change driven by the project is described as the:
Good state
Future state
Happy state
Transition state
Answer explanation
Before the project begins, the organization is commonly referred to as being in the current state. The desired result of the change derived by the project is described as the future state.
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The term Progressive Elaboration incorrectly represents which of the following?
Changes to project scope
Rolling wave planning
Detailing out the product requirements developed during the initiation process.
Production of fabrication and construction drawings from the design drawings for a chemical plant.
Answer explanation
The distinction between progressive elaboration and scope creep needs to be understood since the two terms are different. The changes to scope (especially in an uncontrolled manner) are called scope creep. In contrast, progressive elaboration involves building on or elaborating the output of a previous phase.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which document describes the project's deliverables and the work required to create those deliverables?
Project authorization document
Project scope statement
Project scope management plan
Project charter
Answer explanation
The project scope statement is the correct response. This document describes the project's deliverables in detail and the work that is required to create those deliverables. It also forms the baseline for evaluating whether requests for changes are within or outside the project's boundaries.
Create a free account and access millions of resources
Similar Resources on Quizizz
8 questions
Quiz Lesson 6 - Topic B (Benefits Realization)

Quiz
•
Professional Development
6 questions
Validate and Control Scope - Assignment

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic C (Schedule)

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic D (Resources and Procurement)

Quiz
•
Professional Development
10 questions
Resource Mgmt Pre-test

Quiz
•
Professional Development
7 questions
Subsidery Plan - Assignment

Quiz
•
Professional Development
10 questions
Project Management Master Class 3

Quiz
•
Professional Development
10 questions
Project Management

Quiz
•
Professional Development
Popular Resources on Quizizz
10 questions
Chains by Laurie Halse Anderson Chapters 1-3 Quiz

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
15 questions
Character Analysis

Quiz
•
4th Grade
12 questions
Multiplying Fractions

Quiz
•
6th Grade
30 questions
Biology Regents Review #1

Quiz
•
9th Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
50 questions
Biology Regents Review: Structure & Function

Quiz
•
9th - 12th Grade