1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a daily standup meeting, the project team raises a risk that was not identified earlier in project planning. The team discusses the risk with the project manager, who realizes that a potential response to the risk is beyond his authority. Therisk management plan does not provide any guidance on how this type of risk should be managed. What is the project manager's best strategy to deal with this risk?
Capture the risk in the project risk register and develop the appropriate risk response
Conduct a risk-based spike at the beginning of the next iteration to find a potential solution
Perform a risk review to research, analyze, and apply any identified mitigation strategies
Adopt risk escalation as a response strategy so that the risk can be appropriately managed
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a sprint review, the product owner rejects a deliverable stating that it doesn't meet the acceptance criteria. The quality assurance team, who verified the deliverable as part of the Control Quality process, argues that there is nothing wrong with deliverable and that it should be accepted. The product owner disagrees and reject the deliverable. What is the project manager's best course of action to ensure that this type of misunderstanding does not recur?
Perform a root cause analysis during the next sprint review and record the knowledge gained in the lesson learned register
Discuss the problem during the next daily scrum meeting and resolse the misunderstanding between the product owner and team
At the upcoming sprint retrospective meeting, facilitate an exercise to identify the underlying cause of the misunderstanding
Submit a change request to modify the Control Quality process based on the recommendations from the team and product owner
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Project Finance (control and reporting)

Quiz
•
Professional Development
10 questions
Project Management Master Class 1

Quiz
•
Professional Development
12 questions
Agile Mindset Quiz

Quiz
•
Professional Development
10 questions
Project Management

Quiz
•
Professional Development
10 questions
PROJECT RISK MANAGEMENT

Quiz
•
Professional Development
15 questions
LO6 Business Case & Benefits Management

Quiz
•
Professional Development
10 questions
Final Quiz - Assignment

Quiz
•
Professional Development
10 questions
Resource Mgmt Pre-test

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade