4 - Executing the Iteration

4 - Executing the Iteration

Professional Development

8 Qs

quiz-placeholder

Similar activities

Week 24

Week 24

Professional Development

9 Qs

Admin SU22 quizz

Admin SU22 quizz

Professional Development

12 Qs

MS Teams & Ribbon Connect

MS Teams & Ribbon Connect

Professional Development

12 Qs

1B- Competetiveness of innovative enterprises

1B- Competetiveness of innovative enterprises

Professional Development

10 Qs

Value and Accelerate PST | Day 2

Value and Accelerate PST | Day 2

Professional Development

10 Qs

Piosenki Polskich Youtuberów

Piosenki Polskich Youtuberów

1st Grade - Professional Development

6 Qs

Getting back to basics

Getting back to basics

Professional Development

7 Qs

Seberapa Kamu Mengenal Seno???

Seberapa Kamu Mengenal Seno???

Professional Development

10 Qs

4 - Executing the Iteration

4 - Executing the Iteration

Assessment

Quiz

Other

Professional Development

Medium

Created by

Claudia Lidia

Used 8+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What are mandatory for a team Kanban board to be effective?

steps of the workflow

stories

WIP limits

feature

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the 'flow distribution' measure?

It measures the number of backlog items completed in a given time frame.

It measures the elapsed time from when an item enters the system to the moment it is delivered to the customer.

It measures the amount of each type of work in the system over time.

It indicates how many items are currently in the system.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which statement is true for Architectural Runway?

It is existing code, hardware components, marketing branding guidelines, etc., that enable near-term business Features.

It is existing hardware and components that enable near-term business Features.

It is existing platform(s) that enable near-term business Features.

It is existing platform(s) managed by System teams that enable near-term business Features

4.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Which statement is true for CLAMR approach to DevOps?

Establish a culture of shared responsibility for development, deployment, and operations.

Architect and enable low-risk releases. Establish fast recovery, fast reversion, and fast fix-forward.

Keep batch sizes small, limit WIP, and provide extreme visibility.

Measure the flow through the pipeline. Implement full-stack telemetry.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What do Burn-up charts show in the Iteration progress?

Estimated versus technical debt

Estimated versus planned

Planned versus actual

Delayed versus deferred

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When are the tests written in a Test-driven Development environment?

While creating the Product Requirements document

Before the code is written

While the code is being written

Just before deployment ("Just in Time")

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do Agile Teams strive to continuously integrate assets?

By integrating vertically sliced user stories

By seeking to physically branch software

By avoiding integrating hardware branches

By leaving as much as possible to the System Team

8.

OPEN ENDED QUESTION

3 mins • 1 pt

For the past week Lee has been late to the Daily Stand-up. Discuss what is the Scrum Master's best course of action?