PM1 - 1.02 (FHS - Moffitt)

PM1 - 1.02 (FHS - Moffitt)

12th Grade

10 Qs

quiz-placeholder

Similar activities

Business finance

Business finance

12th Grade

14 Qs

Strategic Sourcing Quiz

Strategic Sourcing Quiz

9th - 12th Grade

15 Qs

Tallyprime

Tallyprime

10th Grade - Professional Development

11 Qs

Cover Letter and Résumé Quiz

Cover Letter and Résumé Quiz

8th Grade - University

10 Qs

Business Studies Senior Secondary

Business Studies Senior Secondary

12th Grade

10 Qs

Nature and Significance of Management

Nature and Significance of Management

12th Grade

10 Qs

Risk Management Quiz

Risk Management Quiz

12th Grade - University

14 Qs

ENTREPRENEUR CHECK

ENTREPRENEUR CHECK

9th - 12th Grade

10 Qs

PM1 - 1.02 (FHS - Moffitt)

PM1 - 1.02 (FHS - Moffitt)

Assessment

Quiz

Business

12th Grade

Practice Problem

Hard

Created by

Penny Moffitt

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Andrew is the prom committee chairman. He is at the prom and realizes  that the meal delivered to the attendees was steak and not chicken.  

Andrew makes the catering manager aware immediately that the chicken  meal was agreed upon, so the steak meal is outside the project scope.  

Which project management process stage is Andrew in? 

initiating

executing

monitoring and controlling

closing

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Tara is meeting with her stakeholders to determine the scope of work.  What process stage is she in? 

initiating

executing

monitoring and controlling

closing

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Joe holds a team meeting to discuss lessons learned. He is in which  

process stage?

planning

executing

monitoring and controlling

closing

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Andrew is the prom committee chairman. He is on-site at the prom to  make sure all vendors show up at the event and ail vendors’ activities are  falling within the scope of work contracted. Which process stage is  

Andrew in?

initiating

executing

monitoring and controlling

closing

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Sierra is working with her sisters to determine how much money they  have spent on their parents' anniversary party to calculate the funds  

remaining in their budget. What process stage is she in?

initiating

executing

monitoring and controlling

closing

6.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

The organizational structure in which the project manager has the  

greatest amount of authority is a:

composite organization.

functional organization.

matrix organization.

projectized organization.

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Sierra is visiting and calling venues to see who is available to host her  parents’ anniversary party. What process stage is she in?

initiating

executing

monitoring and controlling

closing

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?