1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
Is a house renovation a project or an operation?
project
operation
both
neither
Answer explanation
A house renovation is a project, because it is custom and temporary in nature. It has a start and an end date, and the process is not repeated.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A factory has received a rush order for 100,000 units of toilet rolls for delivery on the 1st of next month. Should the factory setup a project team to run a temporary emergency project to quickly manufacture the 100,000 units, or order the operations division to manufacture 10 batches 10,000 units each?
Commence a special
project to ensure this order is delivered on time.
Order operations to produce the units in 10 batches of 10,000 each.
Reject the order due to time constraints.
Answer explanation
Manufacturing of repeat products is manged by the operations division of a company, not as part of a special project. Operations may manufacture products in batches. In this case, 10 batches of 10,000 units may need to be scheduled. Operations may have multiple, existing orders from other clients that also need to be scheduled, according to pre-established operational rules. These rules may take into account variables such as dead-line, order size, priority and FIFO (first-in, first-out), amongst others.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The operations division have identified the need to reorganize the manufacturing layout of the factory for greater efficiency, with a 25% improvement expected. Operations wants to take care of this during after-hours each night over a period of one month. However, the general manager instead wants to form a new project team to manage the reorganisation, which may result in a shut-down of operations for up to one week during work-hours, and is estimated to require a budget of 50k. What decision should the Managing Director make?
The operations division can take care of the reorganisation after hours as they know the equipment best and can do it cheaply without the need for any shut-down.
A new project team should be formed to plan, allocate and execute the reorganisation, at a cost of 50k and potentially a one week shut-down.
Nothing should be done, as the shut-down will not worth the improvement in efficiency.
A commitee should be setup to research the best approach before making a decision.
Answer explanation
Reorganising operations during after hours is a huge risk to product quality and will very likely take longer than expected. It is also a high-risk strategy, as clearly little planning has been done and no estimate of costs has been given. It is also unclear how the reorganisation could be done bit by bit without affecting current operations.
The best approach of those shown is to setup a project, with allocated funds and a team that can initiate, plan and execute on the reorganisation.
A 25% improvement means that doing nothing is very likely not going to be the best decision, as this is a large improvement.
It is reasonable to undertake more research via a committee, before making the decision. However, the Managing Director may simply opt to authorise the project given the large improvement expected.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is a deliverable?
The desired operational results achieved.
A tangible component or product, document or intangible service or result.
The final output transferred to the customer or to the organisation.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is a project benefit?
The desired operational result achieved from the deliverables.
A description of how to undertake the project work to achieve the project goals.
An advantage accruing from an outcome of a project.
A tangible product, document or an intangible service or result.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is a project objective?
Describes the purpose for which the project was created.
description of how to undertaken the project work.
The final outputs transferred to the customer.
A tangible component or product.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What type of organisational structure is this?
Functional
Project
Matrix
Answer explanation
A matrix organisation is a mix of functional and project organisations, where departments and project managers appear in the organisational structure.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
20 questions
Aggregate Demand and Supply Analysis
Quiz
•
University
20 questions
Tourism Industry
Quiz
•
University
15 questions
theory of production
Quiz
•
University
20 questions
LMCW2153_PENGHAYATAN ETIKA DAN PERADABAN_SET 39 & 40_SEM 1
Quiz
•
University
16 questions
Direitos Humanos
Quiz
•
9th Grade - University
20 questions
theory of demand
Quiz
•
12th Grade - University
16 questions
Jenis-Jenis Karangan dalam Mata kuliah keterampilan menulis
Quiz
•
University
15 questions
How Hong Kong Became a British Colony
Quiz
•
4th Grade - University
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade
Discover more resources for Social Studies
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
9 questions
Principles of the United States Constitution
Interactive video
•
University
18 questions
Realidades 2 2A reflexivos
Quiz
•
7th Grade - University
10 questions
Dichotomous Key
Quiz
•
KG - University
25 questions
Integer Operations
Quiz
•
KG - University
7 questions
What Is Narrative Writing?
Interactive video
•
4th Grade - University
20 questions
SER vs ESTAR
Quiz
•
7th Grade - University