KS Quiz
Quiz
•
Education
•
Professional Development
•
Hard
Dedy Hartanto
Used 2+ times
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 3 pts
During a review meeting, the project manager realizes that scheduled quality control inspections were not conducted. Since the project is running short on time, the project manager decides to hold a joint customer acceptance inspection.
What should the project manager do next?
Advise the team to ensure that all specifications are maintained so the client accepts the deliverable.
Keep the customer informed and seek approvals.
Create a nonconformance report and initiate a corrective action with the project team.
Issue a change request to extend the project schedule to complete the quality checks on time.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
All the technical work on a project has been completed, and the product has been transitioned to an opeartion team.
What should the project manager do before the project can be closed?
Issue a quality report
Validate the scope
Close the contracts
Measure stakeholder satisfaction
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project has been long and difficult. The team is relieved that the project is ending soon, and they begin to submit final reports before an approved one-week break. Overall, the project was successful. However, the project manager realizes that lessons learned were not recorded throughout the project.
Who should the project manager consult during the project to obtain lessons learned?
Project specialist
Project team
Junior project manager
Quality assurance team
4.
MULTIPLE CHOICE QUESTION
1 min • 3 pts
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days.
What should the project manager do?
Check the scope to verify if there is scope creep and get the project on schedule
Submit a change request to the project sponsor to change the schedule
Ask the team to work overtime to complete the deliverable on time
Evaluate the situation and identify ways to compress the schedule without impacting baselines
5.
MULTIPLE CHOICE QUESTION
1 min • 2 pts
A team has been working together for several months and has successfully delivered work. A new team member has joined the team but is having difficulty contributing.
What should the project manager do to help the new team member integrate effectively?
Give the new team member time to contribute until they ask for help and support.
Review the project with the team member to ensure the project scope is understood
Approach the team member to identify any issues and then plan a resolution accordingly.
Assign the new team member tasks so that the team member knows on what to focus.
Similar Resources on Wayground
10 questions
Oil spill Training Quiz
Quiz
•
Professional Development
10 questions
British Values & Prevent
Quiz
•
Professional Development
10 questions
Domains of Learning
Quiz
•
Professional Development
10 questions
Pelatihan Penyambungan DC
Quiz
•
KG - Professional Dev...
10 questions
Lesson Planning
Quiz
•
Professional Development
10 questions
PBL & STEMEC
Quiz
•
Professional Development
10 questions
Diagnostic Quiz
Quiz
•
University - Professi...
10 questions
La Trobe College Aus Quiz
Quiz
•
Professional Development
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
11 questions
NEASC Extended Advisory
Lesson
•
9th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
10 questions
Boomer ⚡ Zoomer - Holiday Movies
Quiz
•
KG - University
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
20 questions
Multiplying and Dividing Integers
Quiz
•
7th Grade