HU_PM_5_Tevékenységek

HU_PM_5_Tevékenységek

University

5 Qs

quiz-placeholder

Similar activities

Les decisions en l'empresa

Les decisions en l'empresa

University

10 Qs

Tema 5

Tema 5

University

10 Qs

Tudás alapfogalmak

Tudás alapfogalmak

University

6 Qs

Post Test Perkembangan Lembaga Keuangan

Post Test Perkembangan Lembaga Keuangan

University

4 Qs

Choreographies, 6-2

Choreographies, 6-2

University

4 Qs

Menedzsment alapjai

Menedzsment alapjai

University

10 Qs

Thunderbird Tutorium

Thunderbird Tutorium

University

10 Qs

GESTIÓ FINANCERA UF2-RA1 Sistema financer i productes i serveis

GESTIÓ FINANCERA UF2-RA1 Sistema financer i productes i serveis

University

10 Qs

HU_PM_5_Tevékenységek

HU_PM_5_Tevékenységek

Assessment

Quiz

Business

University

Practice Problem

Medium

Created by

Gergő Gajzágó

Used 44+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Mit mutat meg nekünk a feladat-lebontási struktúra (FLS)?

A tevékenységek hosszát

Mit kell tennünk

Mikor kell megtenni és meddig tart

Kinek kell tennie

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Melyik a projektéletciklus első fázisa?

Kezdeményezés

Tervezés

Megvalósítás

Monitoring és ellenőrzés

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Csak a klasszikus (vízeséses) projektnek van életciklusa.

Igaz

Hamis

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Egy feladat/tevékenység hossza általában...

0-8 munkaóra

8-80 munkaóra

8-24 munkaóra

40-80 munkaóra

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Mit mutat a Gantt-diagram?

A tevékenységek költségeit

A tevékenységek listáját és időtartamát

A tevékenységek előfeltételeit

Tevékenységek ganttjait