1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The work breakdown structure is __________ -oriented.
Decomposition
Risk
Deliverable
Action
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project. Which of the following documents contains the detailed description of work packages?
WBS dictionary
Activity List
Project scope statement
Scope management plan
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following statement related to Validate Scope and Quality Control is accurate?
Validate Scope is concerned with correctness of the work results while quality control is primarily concerned with acceptance of the work results
Validate Scope is concerned with acceptance of the work results while quality control is primarily concerned with correctness of the work results
Validate Scope is done only after changes are approved by the change control board
Both Validate Scope and Quality control are always done sequentially
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by the stakeholders’. The BEST thing for the project manager to do is to:
Let the sponsor know of the stake holder’s request
Evaluate the impact of adding the scope
Tell the stakeholder the scope cannot be added
Add the work if the time is available in the project schedule
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The Work Breakdown Structure can BEST be thought of as an effective aid for __________ communications.
Team
Project manager
Customer
Stakeholder
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is the KEY output of Validate Scope process?
A more complete Scope management plan
Customer acceptance of project deliverables
Improved Schedule estimates
An improved Project management information system
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
When decomposing the work in the Work Breakdown Structure (WBS), which of the following is NOT true?
Decompose until the WBS element cannot be logically decomposed further
Decompose until the WBS element can be estimated accurately
Decompose until the WBS element can be accomplished by a single project team member
Decompose until the WBS element has a meaningful conclusion
Create a free account and access millions of resources
Similar Resources on Wayground
15 questions
Scope Management Plan

Quiz
•
Professional Development
7 questions
Scope - Final Quiz - Assignment

Quiz
•
Professional Development
10 questions
Project Scope Management

Quiz
•
Professional Development
6 questions
Validate and Control Scope - Assignment

Quiz
•
Professional Development
10 questions
Project Integration Revision

Quiz
•
Professional Development
9 questions
Planning and Scheduling Professional Practice Questions

Quiz
•
Professional Development
10 questions
IT Project Management - IT Project Planning

Quiz
•
Professional Development
10 questions
Practice Exam 2 Part 2

Quiz
•
Professional Development
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade