A project manager works at a EPCI company. The current project is a three year, multimillion-dollar initiative to build a FPSO. The first phase of the project has been completed within the six months timeframe and within budget. What should the project manager do next?
PMP Exam Trial

Quiz
•
Business
•
Professional Development
•
Medium
dwi rakhmatullah
Used 29+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Move on to the next phase
Secure approval from the program manager
Proceed with the contractual closure of the phase
Begin the administrative closure process
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During the project closing, the project sponsor informs the project manager that one of the deliverables, developed by a contractor, must be transferred to a nonprofit organization at no cost. The procurement documentation states that the property of this deliverable reverts to the contractor once the procurement contract is finished.
What should the project manager do?
Add "avoid out of scope agreements during the closure process" to the lessons learned register
Initiate a change request and execute the integrated change control process
Consider this transfer as an open issue for the contract department and continue closing the project
Review the contract agreement with the contractor in order to modify the property of the deliverable
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
At project initiation, a quote for the required services was requested from a vendor, and the work was estimated at US$100,000. As the project progressed, requirements were updated following the company's procurement process, and a modified quote was received for more than US$250,000. The allocated contingency funds are not sufficient to cover the difference. What should the project manager do?
Restart the procurement process and select a new vendor
Review the contract type that will be awarded to the vendor
Proceed with the best offer as per the procurement process
Engage the steering committee and escalate the issue
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A company that has traditionally used predictive approaches has been experimenting with the use of agile in portions of a project. Because the company has been pleased with the results, the project sponsor now requests that the entire project be converted to agile. What should the project manager do?
Propose that the approach change to agile take effect for new projects
Submit a change request to the change control board (CCB)
Consult the product owner as they may have reasons to continue using a predictive approach
Convert the project deliverables to user stories and inform the team
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager in a quickly growing hybrid organization is becoming increasingly frustrated at the rapid amount of change in daily operations. Several newer team members have already left the team or have been promoted to other roles in the organization.
What should the project manager do to ensure the project governance remains stable?
Work with senior leadership to update the organizational process assets
Develop a new social contract to empower the team
Update the team charter with new team members
Update the project management plan on a regular basis
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A company used to deliver technical services to customers using external labor. When a new project manager arrived, the team hired specialized personnel to reduce costs by delivering an in-house service. Some of the stakeholders are frustrated that the resources are taking too much time to deliver the service.
What should the project manager do to address the concern?
Ask the functional manager to run a survey after the service delivery
Increase stakeholders' understanding of the project approach
Rehire the external contractor who provided the service previously
Develop a glide path and communicate the ramp-up plan to stakeholders
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager has been asked to manage an existing complex project. Some goals have already been delivered by the previous project manager. While reviewing the project management plan, the project manager realizes that one of the key deliverables is missing from the project goal.
What should the project manager do next to ensure the expected project value is delivered?
Escalate the issue about the deliverable to the project sponsor
Confirm the expected deliverables and rebaseline the project
Track through Requirements Traceability Matrix
Use the contingency fund for more resources to complete the missing deliverable.
Create a free account and access millions of resources
Similar Resources on Quizizz
11 questions
Team Meeting

Quiz
•
Professional Development
15 questions
Diplomado Intec - Ágil

Quiz
•
Professional Development
14 questions
Scrum Training - day 1

Quiz
•
Professional Development
6 questions
CAPM | Day 3

Quiz
•
Professional Development
10 questions
FS Townhall Quiz

Quiz
•
Professional Development
10 questions
Lesson 6 | Close the Project/Phase

Quiz
•
Professional Development
9 questions
AgilePM Roles & Responsibilities

Quiz
•
Professional Development
8 questions
AgilePM (Roles & Responsibilies)

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade