PMP Exam Trial

PMP Exam Trial

Professional Development

10 Qs

quiz-placeholder

Similar activities

BA Revision Session 1 - The Organisation

BA Revision Session 1 - The Organisation

Professional Development

11 Qs

SSIHM C2

SSIHM C2

University - Professional Development

13 Qs

Level 3 EAL 002 Unit LO-3 Quiz-1

Level 3 EAL 002 Unit LO-3 Quiz-1

Professional Development

12 Qs

Careers Week - Getting to know CXO

Careers Week - Getting to know CXO

Professional Development

15 Qs

BIA - BCP Refresher Quiz

BIA - BCP Refresher Quiz

Professional Development

10 Qs

Introduction to Management

Introduction to Management

University - Professional Development

10 Qs

Organization Capability Quiz

Organization Capability Quiz

Professional Development

8 Qs

Leadership & Management

Leadership & Management

Professional Development

10 Qs

PMP Exam Trial

PMP Exam Trial

Assessment

Quiz

Business

Professional Development

Medium

Created by

dwi rakhmatullah

Used 29+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager works at a EPCI company. The current project is a three year, multimillion-dollar initiative to build a FPSO. The first phase of the project has been completed within the six months timeframe and within budget. What should the project manager do next?

Move on to the next phase

Secure approval from the program manager

Proceed with the contractual closure of the phase

Begin the administrative closure process

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During the project closing, the project sponsor informs the project manager that one of the deliverables, developed by a contractor, must be transferred to a nonprofit organization at no cost. The procurement documentation states that the property of this deliverable reverts to the contractor once the procurement contract is finished.

What should the project manager do?

Add "avoid out of scope agreements during the closure process" to the lessons learned register

Initiate a change request and execute the integrated change control process

Consider this transfer as an open issue for the contract department and continue closing the project

Review the contract agreement with the contractor in order to modify the property of the deliverable

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

At project initiation, a quote for the required services was requested from a vendor, and the work was estimated at US$100,000. As the project progressed, requirements were updated following the company's procurement process, and a modified quote was received for more than US$250,000. The allocated contingency funds are not sufficient to cover the difference. What should the project manager do?

Restart the procurement process and select a new vendor

Review the contract type that will be awarded to the vendor

Proceed with the best offer as per the procurement process

Engage the steering committee and escalate the issue

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A company that has traditionally used predictive approaches has been experimenting with the use of agile in portions of a project. Because the company has been pleased with the results, the project sponsor now requests that the entire project be converted to agile. What should the project manager do?

Propose that the approach change to agile take effect for new projects

Submit a change request to the change control board (CCB)

Consult the product owner as they may have reasons to continue using a predictive approach

Convert the project deliverables to user stories and inform the team

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager in a quickly growing hybrid organization is becoming increasingly frustrated at the rapid amount of change in daily operations. Several newer team members have already left the team or have been promoted to other roles in the organization.

What should the project manager do to ensure the project governance remains stable?

Work with senior leadership to update the organizational process assets

Develop a new social contract to empower the team

Update the team charter with new team members

Update the project management plan on a regular basis

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A company used to deliver technical services to customers using external labor. When a new project manager arrived, the team hired specialized personnel to reduce costs by delivering an in-house service. Some of the stakeholders are frustrated that the resources are taking too much time to deliver the service.

What should the project manager do to address the concern?

Ask the functional manager to run a survey after the service delivery

Increase stakeholders' understanding of the project approach

Rehire the external contractor who provided the service previously

Develop a glide path and communicate the ramp-up plan to stakeholders

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager has been asked to manage an existing complex project. Some goals have already been delivered by the previous project manager. While reviewing the project management plan, the project manager realizes that one of the key deliverables is missing from the project goal.

What should the project manager do next to ensure the expected project value is delivered?

Escalate the issue about the deliverable to the project sponsor

Confirm the expected deliverables and rebaseline the project

Track through Requirements Traceability Matrix

Use the contingency fund for more resources to complete the missing deliverable.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?