[SAFETY GAP CLOSURE] PSM

[SAFETY GAP CLOSURE] PSM

Professional Development

15 Qs

quiz-placeholder

Similar activities

ED UNIT NO. 1

ED UNIT NO. 1

Professional Development

10 Qs

Lesson 4:  SD Methodologies. Discussing Waterfall, Agile & Scrum

Lesson 4: SD Methodologies. Discussing Waterfall, Agile & Scrum

Professional Development

10 Qs

HSE Life Saving Rules

HSE Life Saving Rules

Professional Development

15 Qs

Quiz Competition

Quiz Competition

Professional Development

10 Qs

HSE SUMMIT 2020

HSE SUMMIT 2020

10th Grade - Professional Development

10 Qs

Unit 201 Health and safety

Unit 201 Health and safety

Professional Development

20 Qs

TRAIN THE TRAINER - DEFINE TRAINING NEEDS (CU1)

TRAIN THE TRAINER - DEFINE TRAINING NEEDS (CU1)

Professional Development

15 Qs

Lean Startup

Lean Startup

Professional Development

10 Qs

[SAFETY GAP CLOSURE] PSM

[SAFETY GAP CLOSURE] PSM

Assessment

Quiz

Other

Professional Development

Medium

Created by

Ghadafi Ismail

Used 5+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Following is the purpose of Pre-Startup Safety Review (PSSR) EXCEPT:

Construction and equipment are in accordance with the design specifications

Procedure is in place and adequate

Training for each affected employee by the changes has been completed

Can meet the project timeline

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Pre-Startup Safety Review (PSSR) shall be performed before a chemical is stored on site at the new or modified facility or equipment or before a chemical is introduce into processing equipment for shutdown facility.

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Approval by Authority (e.g., DOSH, DOE, BOMBA, etc.) is one of the items that will be verified during Pre-Startup Safety Review (PSSR).

True

False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Below is the example of changes requiring Management of Change (MOC) to be requested except:

Change the raw material supplier

Change the pump type

Installation of a new production line

Change the process parameter

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Shift Supervisor noticed a faulty PSV and plan to isolate the PSV for repairing work. Which procedure shall the Shift Supervisor follow?

MOC Procedure

Bypass Management of SCE

6.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Select all the mandatory approver for Bypass application during "Normal Operation".

Head of Department

Solution Vehicle (SV) Head

SHEQ Division Head

Plant General Manager (PGM)

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

MOC shall be requested and approved at which stage?

During commissioning

Before change being implemented

90 days after commissioning

After HOD requested

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?