PM1 Unit 4 Estimations

PM1 Unit 4 Estimations

9th - 12th Grade

5 Qs

quiz-placeholder

Similar activities

Čepy

Čepy

12th Grade

10 Qs

Golisano Institute for Business & Entrepreneurship Quiz

Golisano Institute for Business & Entrepreneurship Quiz

10th Grade

10 Qs

Unit 7 - ความปลอดภัยเกี่ยวกีบไฟฟ้า

Unit 7 - ความปลอดภัยเกี่ยวกีบไฟฟ้า

12th Grade

10 Qs

Pre-Test: Assess Quality of Received Materials

Pre-Test: Assess Quality of Received Materials

9th Grade

5 Qs

Lesson 1 Introduction to Database System

Lesson 1 Introduction to Database System

10th Grade

10 Qs

Умный дом с Алисой

Умный дом с Алисой

9th - 12th Grade

9 Qs

Análisis población

Análisis población

11th Grade

10 Qs

Desenvolvimento de Sistemas

Desenvolvimento de Sistemas

9th Grade

10 Qs

PM1 Unit 4 Estimations

PM1 Unit 4 Estimations

Assessment

Quiz

Instructional Technology

9th - 12th Grade

Hard

Created by

Bobbie Jones

Used 2+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager estmates that most likely a rodeo will take 3 months to produce, an optomistic timeline would be 1 month will be, and if lots goes wrong it will take up to 7 months. What estimate should they give using the 3-point method? TE=(O+4L+P)/6

4 months

3 months 10 days

3.5 months

20 months 2 days

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager estmates that most likely a rodeo will cost $14,000 to produce, an optomistic cost would be $10,000, and if lots goes wrong it will take up to $27,000. What cost estimate should they give using the 3-point method?

TE=(O+4L+P)/6

$15,600

$13,500

$30,000

$15,500

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager estmates that most likely a rodeo will cost $14,000 to produce, an optomistic cost would be $10,000, and if lots goes wrong it will take up to $27,000. What cost estimate should they give using a 20% extra reserve analysis with the 3 point method?

TE=(O+4L+P)/6

$18,600

$30,000

$14,850

$16,800

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A team is using vendor analysis with quotes to determine what to charge for hosting a competitive event at their local community center. Vendor A quoted $8,000, Vendor B quoted $10,500, and Vendor C quoted $5,500. What would be a safe quote to give based on vendor analysis?

$9,000

$8,000

$10,500

$5,500

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An the expert wedding planner tells you that the wedding described should cost $15,000 with 300 memebers. What will you quote if the customer decides on 500 guests using the parametric method?

$25,000

$15,000

$20,000

$30,000