MA - Mock 2 (2023)

Quiz
•
Other
•
Professional Development
•
Medium
PFC Education
Used 33+ times
FREE Resource
44 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The following information is available for two projects. Only one project can be undertaken.
Which TWO of the following statements are TRUE?
(a) Project B should be accepted because it has the higher IRR
(b) Project A should be accepted because it has the higher NPV
(c) Ranking the projects based on discounted payback period would make project B seem more favourable
(d) At a cost of capital of 17% project B would have a zero NPV
(a) & (b)
(b) & (d)
(c) & (d)
(b) & (c)
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Is each of the following statements about scatter diagrams true or false?
1. Scatter diagrams are graphs which show equations
2. The x-axis on a scatter diagram is used to represent the independent variable
False & False
True & True
False & True
True & False
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A company uses standard marginal costing. Last month when all sales were at the standard price, the standard contribution from the actual sales was $50,000 and the following variances arose:
What was the actual contribution for last month?
$ 40,500
$ 37,500
$ 36,500
$ 46,500
4.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The operating statement used by an organisation to measure the performance of its divisions is structured as follows:
Which of the following would provide the best basis for measuring the performance of a manager of an investment centre?
Divisional net profit
Contribution
Controllable operating profit
Traceable divisional profit
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A company uses standard costing. This year the standard labour cost of a product is $180.60 per unit. The standard labour rate is $86.00 per hour. Last month 2,200 hours were worked and there was an adverse labour efficiency variance of $8,600. This variance was caused entirely by new working practices introduced by the company. The full effect of the new working practices is to be incorporated into the new standard cost of the product for next year. In addition, a labour rate increase of 10% is to be built into the new standard cost.
What is the standard labour cost per unit of the product for next year?
$189.20
$198.66
$208.12
$207.26
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which TWO of the following statements about responsibility centres are true?
(A) A cost which is not controllable by a junior manager may be controllable by a senior manager
(B) The performance of a profit centre is measured by its return on capital
(C) Managers of cost centres should be accountable for controllable costs only
(D) There are only two types of responsibility centre
(A) & (C)
(B) & (C)
(A) & (B)
(C) & (D)
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following methods of costing describes target costing?
A method whose target is to reduce unit cost without impairing the value to the customer
A method that targets selected business departments and aims to minimise their costs
A method that sets a cost by subtracting a desired profit margin from a competitive market price
A method that sets a target price by adding a desired profit margin to actual cost
Create a free account and access millions of resources
Similar Resources on Wayground
45 questions
MC Aéro Module M13.17-22 - Entrainement

Quiz
•
Professional Development
40 questions
Evaluación Tipo A

Quiz
•
Professional Development
40 questions
การปฏิบัติงานในสถานีบริการคาลเท็กซ์

Quiz
•
Professional Development
46 questions
Permit Test

Quiz
•
Professional Development
40 questions
Cajeros Generales - Receptores

Quiz
•
Professional Development
45 questions
What Starbucks drink is this

Quiz
•
KG - Professional Dev...
49 questions
2018 International Plumbing Code

Quiz
•
Professional Development
43 questions
Common Plumbing Processes C&G 8202 6035

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade