CMA 490 - Chapter 4 Review

CMA 490 - Chapter 4 Review

University

30 Qs

quiz-placeholder

Similar activities

Standards of Professional Practice  201 (SPP) Quiz

Standards of Professional Practice 201 (SPP) Quiz

University

25 Qs

BUILDING TECHNOLOGY 4

BUILDING TECHNOLOGY 4

University

25 Qs

FINAL EXAM ODAR3

FINAL EXAM ODAR3

University

25 Qs

Operating System Quiz 2

Operating System Quiz 2

4th Grade - University

35 Qs

ABT Midterm Exam

ABT Midterm Exam

University

30 Qs

INTRODUCTION TO MANAGEMENT

INTRODUCTION TO MANAGEMENT

University

25 Qs

BUILTECH1 FINAL EXAM

BUILTECH1 FINAL EXAM

University

25 Qs

Test 2 Inequalities/ Final Review Algebra 1

Test 2 Inequalities/ Final Review Algebra 1

2nd Grade - University

30 Qs

CMA 490 - Chapter 4 Review

CMA 490 - Chapter 4 Review

Assessment

Quiz

Architecture

University

Easy

Created by

Jeremiah Arnett

Used 2+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

From a project management and scheduling perspective, the challenge of completing a project is maximizing resources without ___.

compromising any project goals

the use of multiple subcontractors

overloading activity schedules

going overbudget

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

___ is the set of financial assets needed to complete a construction project.

Profit

Escrow

Supply

Capital

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The planning of a project begins by developing a(n) ___ and identifying the activities that are required to complete the project.

employee list

work breakdown structure (WBS)

financial bid

critical path (CP)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A(n) ___ schedule is a schedule in which the resources for a project are assigned to activities so that the activities can be closely monitored.

activity-loaded

X-day

resource-loaded

breakdown

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The ___ process involves ensuring that resources have the expertise required by checking bonding information, past projects, and references.

prequalification

research

cataloging

bidding

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ___ constraint is a limitation in which one activity cannot occur until another activity is completed or, in some cases, near completion.

time

technical

resource

physical

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An example of resolving a technical constraint is dividing the floor and the corresponding walls of a building into quadrants based on ___.

building level (1st floor, 2nd floor, etc.)

room type (common room, bathroom, kitchen, etc.)

compass directions (NE, NW, SE, & SW)

size (6', 8', 10', etc.)

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?