
Quiz - Exin Agile Scrum Foundation

Quiz
•
Professional Development
•
Professional Development
•
Hard
Training eNetwoQ ServIT Indonesia
Used 4+ times
FREE Resource
40 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Helping stakeholders understand the Scrum framework and its practices
Keeping high priority features at the top of the product backlog
Preventing changes to the sprint backlog items once the sprint begins
Answer explanation
A) Correct. This is the responsibility of the Scrum Master. (Literature: A, Chapter 2.3.1)
B) Incorrect. This is the responsibility of the Product Owner.
C) Incorrect. No changes should be made to the sprint backlog items, but this is the responsibility of the entire Scrum team, not of the Scrum Master alone.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
This Developer
The Developers
The Product Owner
The Scrum Master
Answer explanation
A) Incorrect. This single Developer might be working on the task, but all Developers stay accountable.
B) Correct. A Developer might work on a task alone, but all Developers share accountability for the development of the product. (Literature: A, Chapter 2.3.1)
C) Incorrect. The Product Owner is not accountable for individual tasks. The Product Owner is accountable for the product backlog.
D) Incorrect. The Scrum Master is accountable for the Scrum team following the Scrum processes, not for this single task.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
It ensures commitment of the Scrum team.
It facilitates osmotic communication.
It minimizes the waste of time.
Answer explanation
A) Incorrect. Commitment of the Scrum team is not based on time-boxing.
B) Incorrect. Osmotic communication means that people gain useful information by overhearing and get involved and help each other as needed.
C) Correct. In Scrum, meetings with fixed objectives and maximum durations (time-boxes) are preferred over ad-hoc meetings. Time-boxing limits the time spent on meetings. (Literature: A, Chapter 1.1.2)
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Developer
Product Owner
Project manager
Scrum Master
Answer explanation
A) Incorrect. The Developers focus on developing backlog items.
B) Incorrect. The Product Owner is accountable for the product backlog.
C) Incorrect. There is no project manager role in Scrum.
D) Correct. The work of this project coordinator is like that of the Scrum Master. (Literature: A, Chapter 2.3.1)
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The Developers'
The Product Owner's
The Scrum Master's
The subject matter expert's
Answer explanation
A) Correct. The Developers are responsible for all estimates. They are the people who will be doing the work and they know best how much effort it takes. No one else can override their estimates. (Literature: A, Chapter 2.3.3)
B) Incorrect. The Product Owner determines what should be estimated but has no control over the estimate itself.
C) Incorrect. The Scrum Master has a say in choosing the process of estimating but has no control over the final estimate.
D) Incorrect. The estimation is made by Developers. People outside the Scrum team, for example subject matter experts, have no control over estimation of product backlog items.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Cancel the rest of the sprint and start a new sprint with new items
Extend the length of the sprint and see if done items can be perfectioned
Pick the next item from the top of the product backlog and add it to the sprint backlog
Shorten the length of the current sprint and shorten the next sprints as well
Answer explanation
A) Incorrect. A sprint can be cancelled in case the sprint goal becomes obsolete. In this case, the sprint goal still makes sense, and the sprint should not be cancelled.
B) Incorrect. Once a sprint begins, its duration is fixed and cannot be shortened or extended.
C) Correct. If all the items are done in the middle of a sprint, the next item from the top of the product backlog can be added to the sprint backlog. (Literature: A, Chapter 2.3.3)
D) Incorrect. Once a sprint begins, its duration is fixed and cannot be shortened or extended. Instead of shortening next sprints, it is better to select more work for the next sprints.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Ensure that all Scrum team members receive all information
Hold the daily scrum together even if office hours do not overlap
Use the osmotic communication technique for disputes
Answer explanation
A) Correct. Whether by means of e-mail, shared documents, or a communication tool, collaboration in a
virtual team is most helped by making sure everyone has access to all information and is kept up to date. (Literature: A, Chapter 3.3)
B) Incorrect. This would cause some members to join the daily scrum outside office hours. This is not the best way to improve the effectiveness of this virtual team.
C) Incorrect. Osmotic communication is primarily used for collocated teams.
Create a free account and access millions of resources
Similar Resources on Quizizz
39 questions
AWS Practitioner 06

Quiz
•
Professional Development
39 questions
Salesforce Admin Certification - SP21 - Set # 2

Quiz
•
Professional Development
37 questions
THC paiement international

Quiz
•
Professional Development
45 questions
SAFe 6.0 Agility - Practice Test

Quiz
•
Professional Development
40 questions
Vaga - Scrum Master

Quiz
•
Professional Development
40 questions
Teko Data Clan - Scrum Quiz #1 - Scrum Roles

Quiz
•
12th Grade - Professi...
35 questions
Scrum Master Certification1

Quiz
•
Professional Development
38 questions
NRF Customer Service & Sales Chp. 2 Review

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade