Quiz - Exin Agile Scrum Foundation

Quiz - Exin Agile Scrum Foundation

Professional Development

40 Qs

quiz-placeholder

Similar activities

PSM 1 - COMPLETO

PSM 1 - COMPLETO

Professional Development

40 Qs

Teko Data Clan - Scrum Quiz #1 - Scrum Roles

Teko Data Clan - Scrum Quiz #1 - Scrum Roles

12th Grade - Professional Development

40 Qs

Scrum Foundation

Scrum Foundation

Professional Development

36 Qs

SEQUAL-SIM EXAM 5:CERTIFICATE IN PROFESSIONAL SCRUM MASTER

SEQUAL-SIM EXAM 5:CERTIFICATE IN PROFESSIONAL SCRUM MASTER

Professional Development

40 Qs

Pensamiento Ágil y Marco Scrum

Pensamiento Ágil y Marco Scrum

Professional Development

40 Qs

SEQUAL-SCRUM PO-SIM EXAM 2

SEQUAL-SCRUM PO-SIM EXAM 2

Professional Development

40 Qs

SMPC - Test 01

SMPC - Test 01

Professional Development

40 Qs

Vaga - Scrum Master

Vaga - Scrum Master

Professional Development

40 Qs

Quiz - Exin Agile Scrum Foundation

Quiz - Exin Agile Scrum Foundation

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Training eNetwoQ ServIT Indonesia

Used 4+ times

FREE Resource

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

Helping stakeholders understand the Scrum framework and its practices

Keeping high priority features at the top of the product backlog

Preventing changes to the sprint backlog items once the sprint begins

Answer explanation

A) Correct. This is the responsibility of the Scrum Master. (Literature: A, Chapter 2.3.1)

B) Incorrect. This is the responsibility of the Product Owner.

C) Incorrect. No changes should be made to the sprint backlog items, but this is the responsibility of the entire Scrum team, not of the Scrum Master alone.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During a sprint, a Developer is working on a task. Who is accountable for this task?

This Developer

The Developers

The Product Owner

The Scrum Master

Answer explanation

A) Incorrect. This single Developer might be working on the task, but all Developers stay accountable.

B) Correct. A Developer might work on a task alone, but all Developers share accountability for the development of the product. (Literature: A, Chapter 2.3.1)

C) Incorrect. The Product Owner is not accountable for individual tasks. The Product Owner is accountable for the product backlog.

D) Incorrect. The Scrum Master is accountable for the Scrum team following the Scrum processes, not for this single task.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

All Scrum events are time-boxed events. What is the advantage of time-boxing?

It ensures commitment of the Scrum team.

It facilitates osmotic communication.

It minimizes the waste of time.

Answer explanation

A) Incorrect. Commitment of the Scrum team is not based on time-boxing.

B) Incorrect. Osmotic communication means that people gain useful information by overhearing and get involved and help each other as needed.

C) Correct. In Scrum, meetings with fixed objectives and maximum durations (time-boxes) are preferred over ad-hoc meetings. Time-boxing limits the time spent on meetings. (Literature: A, Chapter 1.1.2)

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A team is transitioning to Scrum. They already had a role called project coordinator, who helps creating a smooth working environment for all project members. What is accountable for this after the transition? creating a smooth working environment for all project members.

Developer

Product Owner

Project manager

Scrum Master

Answer explanation

A) Incorrect. The Developers focus on developing backlog items.

B) Incorrect. The Product Owner is accountable for the product backlog.

C) Incorrect. There is no project manager role in Scrum.

D) Correct. The work of this project coordinator is like that of the Scrum Master. (Literature: A, Chapter 2.3.1)

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A Product Owner wants a product backlog item to be completed in two days. The Developers working on the item think it will take five days to complete it. The Scrum Master thinks it takes three days. A subject matter expert, who has worked on similar items in the past, thinks it should be at most a one-day effort. Whose estimate should be used for planning?

The Developers'

The Product Owner's

The Scrum Master's

The subject matter expert's

Answer explanation

A) Correct. The Developers are responsible for all estimates. They are the people who will be doing the work and they know best how much effort it takes. No one else can override their estimates. (Literature: A, Chapter 2.3.3)

B) Incorrect. The Product Owner determines what should be estimated but has no control over the estimate itself.

C) Incorrect. The Scrum Master has a say in choosing the process of estimating but has no control over the final estimate.

D) Incorrect. The estimation is made by Developers. People outside the Scrum team, for example subject matter experts, have no control over estimation of product backlog items.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Halfway through a sprint, a team has finished all sprint backlog items. What is the best action to take?

Cancel the rest of the sprint and start a new sprint with new items

Extend the length of the sprint and see if done items can be perfectioned

Pick the next item from the top of the product backlog and add it to the sprint backlog

Shorten the length of the current sprint and shorten the next sprints as well

Answer explanation

A) Incorrect. A sprint can be cancelled in case the sprint goal becomes obsolete. In this case, the sprint goal still makes sense, and the sprint should not be cancelled.

B) Incorrect. Once a sprint begins, its duration is fixed and cannot be shortened or extended.

C) Correct. If all the items are done in the middle of a sprint, the next item from the top of the product backlog can be added to the sprint backlog. (Literature: A, Chapter 2.3.3)

D) Incorrect. Once a sprint begins, its duration is fixed and cannot be shortened or extended. Instead of shortening next sprints, it is better to select more work for the next sprints.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A virtual team with people from two different time zones is working on a project. The team members do not have overlapping office hours, which causes them to be less effective than they hoped for. How can the effectiveness of this virtual team best be improved?

Ensure that all Scrum team members receive all information

Hold the daily scrum together even if office hours do not overlap

Use the osmotic communication technique for disputes

Answer explanation

A) Correct. Whether by means of e-mail, shared documents, or a communication tool, collaboration in a

virtual team is most helped by making sure everyone has access to all information and is kept up to date. (Literature: A, Chapter 3.3)

B) Incorrect. This would cause some members to join the daily scrum outside office hours. This is not the best way to improve the effectiveness of this virtual team.

C) Incorrect. Osmotic communication is primarily used for collocated teams.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?