1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does BIM stand for?

Building Imaging Management

Building Information Management

Big Information Modelling

Building Information Modelling

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Is 4D BIM required for a Rail Civil Build-Only contract?

Yes, always

Only when 3D BIM will be available

No

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does BEP stand for?

BIM Execution Plan

BIM Excellence Plan

BIM Execution Proposal

BIM Excellence Proposal

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The 4D BIM requirements can be found in Annex _ of the BIM Specifications.

A

B

C

D

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where applicable, when is the first 4D BLP required to be submitted?

1 month after the Preliminary Design

2 months after the Preliminary Design

1 month after the Pre-final Design

2 months after the Pre-final Design

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the requirements below are NOT prescribed in the latest Annex D (Civil OR E&M)?

4D BLP requirements

4D CIP Requirements

BEP Requirements

4D BIM Training Requirements

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where applicable, which of the following aspects of the programme do not have to be simulated in a 4D BLP?

Programme Constraints

Temporary Utility Diversion

Testing Activities

Temporary Traffic Diversion

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Microsoft

Continue with Microsoft

or continue with

Facebook

Facebook

Apple

Apple

Others

Others

Already have an account?