9 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does BIM stand for?
Building Imaging Management
Building Information Management
Big Information Modelling
Building Information Modelling
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Is 4D BIM required for a Rail Civil Build-Only contract?
Yes, always
Only when 3D BIM will be available
No
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does BEP stand for?
BIM Execution Plan
BIM Excellence Plan
BIM Execution Proposal
BIM Excellence Proposal
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The 4D BIM requirements can be found in Annex _ of the BIM Specifications.
A
B
C
D
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Where applicable, when is the first 4D BLP required to be submitted?
1 month after the Preliminary Design
2 months after the Preliminary Design
1 month after the Pre-final Design
2 months after the Pre-final Design
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the requirements below are NOT prescribed in the latest Annex D (Civil OR E&M)?
4D BLP requirements
4D CIP Requirements
BEP Requirements
4D BIM Training Requirements
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Where applicable, which of the following aspects of the programme do not have to be simulated in a 4D BLP?
Programme Constraints
Temporary Utility Diversion
Testing Activities
Temporary Traffic Diversion
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?