IPM - Chapter 7 (Cost Management)

IPM - Chapter 7 (Cost Management)

University

11 Qs

quiz-placeholder

Similar activities

BBCF1013 - Principles of Finance - Quiz 1

BBCF1013 - Principles of Finance - Quiz 1

University

10 Qs

Project Management & Leadership

Project Management & Leadership

University

7 Qs

Activity 12

Activity 12

University

10 Qs

Project Management Network diagram Quiz (Knowledgehut.com blog)

Project Management Network diagram Quiz (Knowledgehut.com blog)

University

15 Qs

PBMS Kumustahan

PBMS Kumustahan

University

10 Qs

Cost Estimating Theory

Cost Estimating Theory

12th Grade - University

16 Qs

Globalization of Electric Vehicles Quiz

Globalization of Electric Vehicles Quiz

University

10 Qs

TOEFL Structure (Skills 46-48)

TOEFL Structure (Skills 46-48)

9th Grade - Professional Development

10 Qs

IPM - Chapter 7 (Cost Management)

IPM - Chapter 7 (Cost Management)

Assessment

Quiz

Education

University

Medium

Created by

Nguyen Thi Vu Ha

Used 7+ times

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.

What kind of estimate is this?

A. Definitive estimate

B. Rough order of magnitude estimate

C. Wide Estimate

D. Plan Estimate

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).

Which of the following is true regarding your project's current situation as reflected by this TCPI value?

A. The project is within budget

B. The project is over budget

C. The project is behind schedule

D. The project is ahead of schedule

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is Cost Variance (CV)?

350

- 75

400

-50

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a project manager working on a project that requires 100 items to be tested, spaced evenly over five weeks. you have just begun week three, with an overall budget of $10,000 to date, you have spent $2,000 with 40 items tested successfully. What does the cost variance (CV) tell you in this circumstance?

The project is proceeding at 100% of the expected rate.

The project is $2000 under budget.

The project is on budget.

The project is getting $2 of work for every dollar spent.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is $200,000 and that of Activity B is $100,000. The planned value of these activities are $180,000 and $80,000 respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.

0.7

0.8

0.9

0.6

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project is estimated to cost $ 50,000 with a timeline of 50 days. After 25 days, the project manager finds that 50% of the project is complete and Actual costs are $ 50,000. What is the Cost Performance Index (CPI) ?
The CPI is 1
The CPI is 1.5
The CPI is 0.5
The CPI is 2

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The estimate at completion (EAC) is typically based on:

The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.

The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).

The earned value (EV) and the actual cost for work completed (AC).

The cost performance index (CPI) and the cost variance (CV).

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?