IPM - Chapter 7 (Cost Management)

Quiz
•
Education
•
University
•
Medium
Nguyen Thi Vu Ha
Used 7+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
A. Definitive estimate
B. Rough order of magnitude estimate
C. Wide Estimate
D. Plan Estimate
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is Cost Variance (CV)?
350
- 75
400
-50
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager working on a project that requires 100 items to be tested, spaced evenly over five weeks. you have just begun week three, with an overall budget of $10,000 to date, you have spent $2,000 with 40 items tested successfully. What does the cost variance (CV) tell you in this circumstance?
The project is proceeding at 100% of the expected rate.
The project is $2000 under budget.
The project is on budget.
The project is getting $2 of work for every dollar spent.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is $200,000 and that of Activity B is $100,000. The planned value of these activities are $180,000 and $80,000 respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.
0.7
0.8
0.9
0.6
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The estimate at completion (EAC) is typically based on:
The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.
The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).
The earned value (EV) and the actual cost for work completed (AC).
The cost performance index (CPI) and the cost variance (CV).
Create a free account and access millions of resources
Similar Resources on Wayground
15 questions
Project Management Network diagram Quiz (Knowledgehut.com blog)

Quiz
•
University
10 questions
All About GPA

Quiz
•
University
8 questions
ECM367 Chapter 2.2

Quiz
•
University
10 questions
Arista Bogor Quiz

Quiz
•
University
10 questions
Topic 1- Introduction to estimating

Quiz
•
University
12 questions
Quizz - Business and Financial Project Management 11/11/2024

Quiz
•
University
11 questions
Indian Economy

Quiz
•
University - Professi...
16 questions
Budgeting

Quiz
•
9th Grade - University
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
10 questions
Afterschool Activities & Sports

Quiz
•
6th - 8th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
15 questions
Cool Tool:Chromebook

Quiz
•
6th - 8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
20 questions
Bullying

Quiz
•
7th Grade
18 questions
7SS - 30a - Budgeting

Quiz
•
6th - 8th Grade