1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
IPM - Chapter 7 (Cost Management)
Quiz
•
Education
•
University
•
Medium
Nguyen Thi Vu Ha
Used 7+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
A. Definitive estimate
B. Rough order of magnitude estimate
C. Wide Estimate
D. Plan Estimate
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is Cost Variance (CV)?
350
- 75
400
-50
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are a project manager working on a project that requires 100 items to be tested, spaced evenly over five weeks. you have just begun week three, with an overall budget of $10,000 to date, you have spent $2,000 with 40 items tested successfully. What does the cost variance (CV) tell you in this circumstance?
The project is proceeding at 100% of the expected rate.
The project is $2000 under budget.
The project is on budget.
The project is getting $2 of work for every dollar spent.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is $200,000 and that of Activity B is $100,000. The planned value of these activities are $180,000 and $80,000 respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.
0.7
0.8
0.9
0.6
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The estimate at completion (EAC) is typically based on:
The actual costs incurred for work completed (AC), and the estimate to complete (ETC) the remaining work.
The actual costs incurred for work completed (AC) and the cumulative cost performance index (CPI).
The earned value (EV) and the actual cost for work completed (AC).
The cost performance index (CPI) and the cost variance (CV).
15 questions
types of inflation
Quiz
•
10th Grade - University
15 questions
Project Management Network diagram Quiz (Knowledgehut.com blog)
Quiz
•
University
16 questions
Cost Estimating Theory
Quiz
•
12th Grade - University
10 questions
Globalization of Electric Vehicles Quiz
Quiz
•
University
8 questions
ECM367 Chapter 2.2
Quiz
•
University
10 questions
TOEFL Structure (Skill 1-14)
Quiz
•
9th Grade - Professio...
15 questions
Project Monitoring Quiz
Quiz
•
University
10 questions
S1.22 BUSM4570 Week 4
Quiz
•
University
15 questions
Multiplication Facts
Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz
Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set
Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025
Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)
Quiz
•
9th - 12th Grade
15 questions
June Review Quiz
Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles
Quiz
•
8th Grade
25 questions
Triangle Inequalities
Quiz
•
10th - 12th Grade